Notes:
POOL AND SPA
10/14/2003 12:00:00 AM
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
24. EXITWAYS (HALLWAYS) MUST BE A MIN. 36"W INCLUDING ARCHED OR CASED OPENINGS. (TWO OR MORE ROOMS)
25. TEMPERED GLASS REQ'D AT WINDOWS WITHIN 2' OF DOOR OPENINGS.
28. TEMPERED GLASS REQ'D AT WINDOW ADJ TO STAIR.
32. SECOND FLOOR SIDING AREA MUST NOT EXCEED 50% OF THE TOTAL NET EXPOSED WALL AREA.
33. MEDIA ROOM WITH STORAGE CLOSET MUST HAVE OPERABLE WINDOW.
35. 2 X 6 PLUMBING (VENT STACK/WASTE)WALLS REQ'D.
44. CO DETECTORS REQ'D ON ELECT LEGEND & ELECT PLAN 1/1000 SQ FT & 1 PER FLOOR MIN PLUS (1) ADD'L AT GARAGE ENTRY IN AC AREA.
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
57. AUTOMATIC FIRE PROTECTION SPRINKLERS REQ'D W/ DESIGN & INSTALLATION APPROVED BY FIRE MARSHAL.
58. 12 SEER ALONG WITH R-6 DUCT WORK REQ'D FOR 2000 IECC COMPLIANCE IN NON ENERGY STAR/GREEN BLDG CONSTRUCTION.
(10/14/2003 15:01 MBW)GRADE BEAMS-10"WX34"D WITH 12" DIAMETER PIERS WITH (4)#5 VERTICAL REBAR.
(2/25/2004 10:40 DEB) DELETED $30 INSPECTION FEE FOR 12/31/03 BRICK/WALL TIES PER DONNIE MAYFIELD.
(3/12/2004 19:37 JS) (3/12/2004 19:37 JS)
DUAL MAIN DRAINS REQUIRED
TURNOVER RATE TO BE LESS THAN 6 HOURS
POOL EQUIPMENT TO BE 5 FEET AWAY FROM ANY OPENABLE WINDOW
BOARD TO MEET NSPI STANDARDS
CONTRACTORS: IT IS YOUR RESPONSIBILITY TO INFORM THE HOMEOWNER OF THE NECESSITY OF INSPECTORS TO GAIN ACCESS TO THE BACKYARD.
CERTIFICATION OF POOL PROTECTION DEVICE INSTALLATION TO BE SIGNED AND ON SITE AT PRE-PLASTER INSPECTION.