Permit Info
Short Description:
4320 SF, SHELL BUILDING 10
Expiration Date:
1/6/2027
Parcel Info
City/State/Zip:
FRISCO, 75035
|
| APPLICANT | Bharath Nandigam | (408)992-5558 | bharath@firstinfra.us | 6600 Paige Rd | The Colony, TX 75056 |
| CONTRACTOR | FIRST INFRA LLC | (937)708-9589 | bharath@firstinfra.us | 6600 Paige Rd Suite 224 | The Colony, TX 75056 |
| ELECT. CTR. | ELECTRA PLUS (ELEC) | (972)607-4197 | electra.plusmty@gmail.com | 321 N ROGERS | IRVING, TX 75061 |
| PLUM. CTR. | ELITE PLUMBING & DRAIN | (817)269-2082 | 817epd@gmail.com | 8585 N. Stemmons Frwy #408S | Dallas, TX 75247 |
|
| FLATWORK COMM 03/31/2026 DC2 |
$75.00
|
4/1/2026
|
| PERCENT CREDIT CARD FEE |
$8.00
|
4/1/2026
|
| PERCENT CREDIT CARD FEE |
$6.50
|
5/28/2026
|
| PERCENT CREDIT CARD FEE |
$1.50
|
6/8/2026
|
| PERCENT CREDIT CARD FEE |
$1.50
|
6/16/2026
|
| COMM BUILDING PERMIT FEE |
$50.00
|
4/1/2026
|
| COMM BUILDING PERMIT FEE |
$50.00
|
4/1/2026
|
| COMMERCIAL RENOVATION FEE |
$50.00
|
5/28/2026
|
| COMM BUILDING PERMIT FEE |
$50.00
|
5/28/2026
|
| PLUMB TOP OUT COMM 05/28/2026 JWR |
$75.00
|
6/8/2026
|
| FRAME COMM 02/23/2026 LUN |
$75.00
|
4/1/2026
|
| FLATWORK COMM 03/30/2026 LUN |
$75.00
|
4/1/2026
|
| ELECT ROUGH COMM 04/29/2026 LUN |
$75.00
|
5/28/2026
|
| ELECT ROUGH COMM 05/04/2026 LUN |
$75.00
|
5/28/2026
|
| FRAME COMM 05/04/2026 LUN |
$75.00
|
5/28/2026
|
| PLUMBING FINAL 06/15/2026 MLM |
$75.00
|
6/16/2026
|
| AUTO PROCESSING FEE |
$6.00
|
5/9/2025
|
| COMMERCIAL FEE |
$202.80
|
7/29/2025
|
| COMMERCIAL BUILDING PERMIT FEE |
$1,313.25
|
7/29/2025
|
| COMMERCIAL MECHANICAL FEE |
$43.50
|
7/29/2025
|
| COMMERCIAL NEW APPLICATION FEE |
$300.00
|
5/9/2025
|
| COMMERCIAL PLUMBING FEE |
$418.80
|
7/29/2025
|
| SEWER IMPACT FEE |
$0.00
|
|
| THOROUGHFARE IMPACT FEE |
$0.00
|
|
| WATER IMPACT FEE |
$0.00
|
|
| PLUMB TOP OUT COMM 03/30/2026 SMH |
$75.00
|
4/1/2026
|
| 2 INCH T-10 METER |
$1,275.00
|
1/22/2026
|
| WATER METER DEPOSIT COMMERCIAL |
$1,100.00
|
1/22/2026
|
| Total Fees |
|
Charged: $5,551.85
Balance Due: $0.00
|
|
| BUILDING FINAL | APPROVED |
7/10/2026
| | 7/10/2026 | |
More Info
|
| INSULATION COMM | APPROVED |
7/10/2026
| | 7/10/2026 | |
More Info
|
| INSULATION COMM | COMM FAILED |
7/9/2026
| | 7/9/2026 | |
More Info
|
| BUILDING FINAL | COMM FAILED |
7/8/2026
| | 7/8/2026 | |
More Info
|
| FIRE FINAL | APPROVED |
7/7/2026
| 11:00 AM | 7/7/2026 | |
More Info
|
| FIRE FINAL | FIRE FAILED |
7/6/2026
| 9:00 AM | 7/6/2026 | |
More Info
|
| FIRE FINAL | CANCELLED |
6/23/2026
| 10:00 AM | 6/23/2026 | |
More Info
|
| BUILDING FINAL | CANCELLED |
6/19/2026
| | 6/19/2026 | |
More Info
|
| PLUMBING FINAL | APPROVED |
6/16/2026
| | 6/16/2026 | |
More Info
|
| PLUMBING FINAL | COMM FAILED |
6/15/2026
| | 6/15/2026 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
6/11/2026
| | 6/11/2026 | |
More Info
|
| PLUMBING FINAL | COMM FAILED |
6/11/2026
| | 6/11/2026 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
6/10/2026
| | 6/10/2026 | |
More Info
|
| PLUMB TOP OUT COMM | COMM FAILED |
6/10/2026
| | 6/10/2026 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
6/10/2026
| | 6/10/2026 | |
More Info
|
| ELECT FINAL COMM | COMM FAILED |
6/8/2026
| | 6/8/2026 | |
More Info
|
| MECHANICAL FINAL | CANCELLED |
6/8/2026
| | 6/8/2026 | |
More Info
|
| FRAME COMM | APPROVED |
5/28/2026
| | 5/28/2026 | |
More Info
|
| PLUMB TOP OUT COMM | COMM FAILED |
5/28/2026
| | 5/28/2026 | |
More Info
|
| PLUMB TOP OUT COMM | CANCELLED |
5/26/2026
| | 5/26/2026 | |
More Info
|
| PLUMB TOP OUT COMM | CANCELLED |
5/18/2026
| | 5/18/2026 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
5/13/2026
| | 5/13/2026 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
5/12/2026
| | 5/12/2026 | |
More Info
|
| PIER COMM | APPROVED |
5/12/2026
| | 5/12/2026 | |
More Info
|
| PLUMB TOP OUT COMM | CANCELLED |
5/8/2026
| | 5/8/2026 | |
More Info
|
| FRAME COMM | COMM FAILED |
5/4/2026
| | 5/4/2026 | |
More Info
|
| ELECT ROUGH COMM | COMM FAILED |
5/4/2026
| | 5/4/2026 | |
More Info
|
| ELECT ROUGH COMM | COMM FAILED |
4/29/2026
| | 4/29/2026 | |
More Info
|
| FLATWORK COMM | APPROVED |
4/1/2026
| | 4/1/2026 | |
More Info
|
| FLATWORK COMM | COMM FAILED |
3/31/2026
| | 3/31/2026 | |
More Info
|
| FLATWORK COMM | COMM FAILED |
3/30/2026
| | 3/30/2026 | |
More Info
|
| PLUMB TOP OUT COMM | COMM FAILED |
3/30/2026
| | 3/30/2026 | |
More Info
|
| UNDERGROUND ELEC | APPROVED |
3/23/2026
| | 3/23/2026 | |
More Info
|
| FLATWORK COMM | CANCELLED |
3/23/2026
| | 3/23/2026 | |
More Info
|
| SET 2 T-10 METER | APPROVED |
3/5/2026
| 8:30 AM | 3/5/2026 | |
More Info
|
| LATH COMM | APPROVED |
2/27/2026
| | 2/27/2026 | |
More Info
|
| FRAME COMM | COMM FAILED |
2/23/2026
| | 2/23/2026 | |
More Info
|
| SET 2 T-10 METER | WM NOT READY |
2/23/2026
| 12:30 PM | 2/23/2026 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
2/10/2026
| | 2/10/2026 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
2/2/2026
| | 2/2/2026 | |
More Info
|
| ELECT ROUGH COMM | COMM FAILED |
1/30/2026
| | 1/30/2026 | |
More Info
|
| ELECT ROUGH COMM | CANCELLED |
1/29/2026
| | 1/29/2026 | |
More Info
|
| ELECT ROUGH COMM | CANCELLED |
1/28/2026
| | 1/28/2026 | |
More Info
|
| ELECT ROUGH COMM | CANCELLED |
1/27/2026
| | 1/27/2026 | |
More Info
|
| SET 2 T-10 METER | WM NOT READY |
1/27/2026
| 8:00 AM | 1/27/2026 | |
More Info
|
| ELECT ROUGH COMM | CANCELLED |
1/26/2026
| | 1/26/2026 | |
More Info
|
| METER PAYMENT | APPROVED |
1/22/2026
| | 1/22/2026 | |
More Info
|
| SHEATHING COMM | APPROVED |
1/16/2026
| | 1/16/2026 | |
More Info
|
| SHEATHING COMM | COMM FAILED |
1/14/2026
| | 1/14/2026 | |
More Info
|
| SLAB COMM | APPROVED |
12/3/2025
| | 12/3/2025 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
11/18/2025
| | 11/18/2025 | |
More Info
|
| PIER COMM | APPROVED |
11/11/2025
| | 11/11/2025 | |
More Info
|
There are currently no reviews on this record.