Permit Info
Short Description:
13200 SF, SHELL
Expiration Date:
1/31/2027
Parcel Info
City/State/Zip:
FRISCO, TX, 75034
Subdivision:
SNELL ADDITION (CFR)
|
| APPLICANT | Polo Padilla | (469)579-2227 | epadilla@idstudio4.com | 6201 Campus Circle Drive E | Irving, TX 75063 |
| OWNER | SCSD-FINNELL LTD | ()- | | | DALLAS, TX 75254-1315 |
| CONTRACTOR | AE Contractors | (214)483-0400 | tlocker@albertenterprises.com | 14114 Dallas Pkwy #670 | Dallas, TX 75254 |
| ELECT. CTR. | G3 Electrical Contractor | (214)435-5569 | brittany@g3longhorns.com | 2802 FM 71 e | Sulphur Springs, tx 75482 |
| PLUM. CTR. | D2 PLUMBING, LLC | (972)741-6262 | D2PLUMBINGLLC@GMAIL.COM | 1030 RILEY ROAD | WHITESBORO, TX 76273 |
|
| NSF RETURN CHECK FEE |
$35.00
|
2/3/2025
|
| PIER COMM 08/28/2025 DC2 |
$35.00
|
8/28/2025
|
| ELECT RELEASE COMM 03/16/2026 DC2 |
$75.00
|
4/21/2026
|
| PERCENT CREDIT CARD FEE |
$0.70
|
2/3/2025
|
| PERCENT CREDIT CARD FEE |
$1.00
|
4/21/2025
|
| PERCENT CREDIT CARD FEE |
$0.70
|
4/22/2025
|
| PERCENT CREDIT CARD FEE |
$47.50
|
5/27/2025
|
| PERCENT CREDIT CARD FEE |
$1.50
|
11/9/2025
|
| PERCENT CREDIT CARD FEE |
$3.00
|
4/21/2026
|
| COMM BUILDING PERMIT FEE |
$50.00
|
4/21/2025
|
| AUTO PROCESSING FEE |
$6.00
|
7/11/2024
|
| COMMERCIAL FEE |
$558.00
|
1/30/2025
|
| COMMERCIAL BUILDING PERMIT FEE |
$5,902.14
|
1/30/2025
|
| COMMERCIAL MECHANICAL FEE |
$690.00
|
1/30/2025
|
| COMMERCIAL NEW APPLICATION FEE |
$300.00
|
7/11/2024
|
| COMMERCIAL PLUMBING FEE |
$1,218.00
|
1/30/2025
|
| SEWER IMPACT FEE |
$10,714.00
|
1/30/2025
|
| THOROUGHFARE IMPACT FEE |
$82,126.00
|
1/30/2025
|
| WATER IMPACT FEE |
$12,718.00
|
1/30/2025
|
| 2 INCH T-10 METER |
$1,275.00
|
5/27/2025
|
| WATER METER DEPOSIT COMMERCIAL |
$1,100.00
|
5/27/2025
|
| PERCENT CREDIT CARD FEE |
$0.70
|
8/28/2025
|
| FRAME AND ELEC WALL 02/26/2026 DC2 |
$75.00
|
4/21/2026
|
| SHEATHING COMM 11/04/2025 DC2 |
$75.00
|
11/9/2025
|
| SLAB COMM 04/22/2025 DC2 |
$35.00
|
4/22/2025
|
| Total Fees |
|
Charged: $117,042.24
Balance Due: $0.00
|
|
| BUILDING FINAL | COMM FAILED |
8/4/2026
| | 8/4/2026 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
7/14/2026
| | 7/14/2026 | |
More Info
|
| BUILDING FINAL | COMM FAILED |
7/14/2026
| | 7/14/2026 | |
More Info
|
| PLUMBING FINAL | APPROVED |
7/14/2026
| | 7/14/2026 | |
More Info
|
| FRAME COMM | APPROVED |
7/14/2026
| | 7/14/2026 | |
More Info
|
| FIRE FINAL | APPROVED |
7/13/2026
| 1:30 PM | 7/13/2026 | |
More Info
|
| FIRE FINAL | FIRE 3RDUP FAILED |
7/8/2026
| 10:30 AM | 7/8/2026 | |
More Info
|
| FIRE FINAL | FIRE 2ND FAILED |
4/28/2026
| 9:00 AM | 4/28/2026 | |
More Info
|
| FIRE FINAL | FIRE FAILED |
4/24/2026
| 1:30 PM | 4/24/2026 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
3/25/2026
| | 3/25/2026 | |
More Info
|
| INSULATION COMM | APPROVED |
3/25/2026
| | 3/25/2026 | |
More Info
|
| FLATWORK COMM | APPROVED |
3/24/2026
| | 3/24/2026 | |
More Info
|
| FLATWORK COMM | CANCELLED |
3/23/2026
| | 3/23/2026 | |
More Info
|
| ELECT RELEASE COMM | COMM FAILED |
3/16/2026
| | 3/16/2026 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
3/16/2026
| | 3/16/2026 | |
More Info
|
| FRAME COMM | PARTIAL APPROVAL |
3/16/2026
| | 3/16/2026 | |
More Info
|
| FLATWORK COMM | APPROVED |
3/3/2026
| | 3/3/2026 | |
More Info
|
| FRAME AND ELEC WALL | COMM FAILED |
2/26/2026
| | 2/26/2026 | |
More Info
|
| UNDERGROUND ELEC | APPROVED |
2/20/2026
| | 2/20/2026 | |
More Info
|
| LATH COMM | APPROVED |
2/5/2026
| | 2/5/2026 | |
More Info
|
| LATH COMM | PARTIAL APPROVAL |
1/13/2026
| | 1/13/2026 | |
More Info
|
| LATH COMM | PARTIAL APPROVAL |
12/12/2025
| | 12/12/2025 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
11/11/2025
| | 11/11/2025 | |
More Info
|
| SHEATHING COMM | APPROVED |
11/10/2025
| | 11/10/2025 | |
More Info
|
| SHEATHING COMM | COMM FAILED |
11/4/2025
| | 11/4/2025 | |
More Info
|
| FRAME COMM | CANCELLED |
11/4/2025
| | 11/4/2025 | |
More Info
|
| FLATWORK COMM | APPROVED |
9/11/2025
| | 9/11/2025 | |
More Info
|
| PIER COMM | APPROVED |
9/2/2025
| | 9/2/2025 | |
More Info
|
| PIER COMM | COMM FAILED |
8/28/2025
| | 8/28/2025 | |
More Info
|
| PIER COMM | CANCELLED |
8/26/2025
| | 8/26/2025 | |
More Info
|
| FOOTINGS COMM | APPROVED |
8/21/2025
| | 8/21/2025 | |
More Info
|
| FIRELANE INSPECTION | APPROVED |
7/31/2025
| 1:30 PM | 7/31/2025 | |
More Info
|
| UNDERGROUND ELEC | APPROVED |
5/29/2025
| | 5/29/2025 | |
More Info
|
| SET 2 T-10 METER | APPROVED |
5/28/2025
| 9:45 AM | 5/28/2025 | |
More Info
|
| METER PAYMENT | APPROVED |
5/27/2025
| | 5/27/2025 | |
More Info
|
| SLAB COMM | APPROVED |
4/30/2025
| | 4/30/2025 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
4/30/2025
| | 4/30/2025 | |
More Info
|
| SLAB COMM | CANCELLED |
4/24/2025
| | 4/24/2025 | |
More Info
|
| SLAB COMM | COMM FAILED |
4/22/2025
| | 4/22/2025 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
3/24/2025
| | 3/24/2025 | |
More Info
|
| FOOTINGS COMM | APPROVED |
2/17/2025
| | 2/17/2025 | |
More Info
|
| PLUMBING ROUGH-IN | CANCELLED |
1/8/2025
| | 1/8/2025 | |
More Info
|
There are currently no reviews on this record.