Permit Info
Short Description:
6403 SF, IVYBROOK ACADEMY
Expiration Date:
4/6/2024
Parcel Info
City/State/Zip:
FRISCO, TX, 75033
Subdivision:
PANTHER CREEK CROSSING
|
| APPLICANT | Lorelei Mewhirter | (469)487-6732 | lorelei.mewhirter@obrienarch.com | 1722 Routh St., Suite 122 | Dallas, TX 75201 |
| OWNER | MULLAPUDI VENTURES LLC | ()- | | | ATLANTA, GA 30339 |
| CONTRACTOR | ML GRAY PARTNERSHIP LLC | (214)628-9425 | dick@MLGRAYPARTNERSHIP.COM | 1811 GREENVILLE AVE STE 150 | DALLAS, TX 75206 |
| ELECT. CTR. | RIGGINS MORELAND ENGINEERING INC | (214)340-1333 | BRANDI@rme-inc.com | 10908 SANDEN DRIVE STE 100 | DALLAS, TX 75238 |
| MECH. CTR. | Alonso Service Company (MECH) | (832)878-6990 | admin@alonsoserviceco.com | 27347 W Hardy Rd | Spring, TX 77373 |
| PLUM. CTR. | D4 PIPING LLC | (916)532-7378 | MICHELLE@D4PIPING.COM | PO Box 1976 | Quinlan, TX 75474 |
| OTHER1 | Alejandro Compian RMP | (972)322-2813 | alexcom78@icloud.com | 10723 Rockingham | Dallas, TX 75217 |
|
| SET 2 T-10 METER 06/16/2023 JRC |
$100.00
|
10/6/2023
|
| WATER IMPACT FEE |
$12,718.00
|
2/8/2023
|
| THOROUGHFARE IMPACT FEE |
$0.00
|
|
| SEWER IMPACT FEE |
$10,714.00
|
2/8/2023
|
| COMMERCIAL PLUMBING FEE |
$606.27
|
2/8/2023
|
| COMMERCIAL NEW APPLICATION FEE |
$300.00
|
7/23/2022
|
| COMMERCIAL MECHANICAL FEE |
$43.50
|
2/8/2023
|
| COMMERCIAL BUILDING PERMIT FEE |
$4,768.14
|
2/8/2023
|
| COMMERCIAL FEE |
$286.12
|
2/8/2023
|
| AUTO PROCESSING FEE |
$6.00
|
7/23/2022
|
| WATER METER DEPOSIT COMMERCIAL |
$1,100.00
|
6/14/2023
|
| 2 INCH T-10 METER |
$1,000.00
|
6/14/2023
|
| COMM BUILDING PERMIT FEE |
$50.00
|
6/14/2023
|
| PERCENT CREDIT CARD FEE |
$2.00
|
10/6/2023
|
| PERCENT CREDIT CARD FEE |
$43.00
|
6/14/2023
|
| Total Fees |
|
Charged: $31,737.03
Balance Due: $0.00
|
|
| BUILDING FINAL | APPROVED |
10/9/2023
| | 10/9/2023 | |
More Info
|
| FIRE FINAL | APPROVED |
8/9/2023
| 11:00 AM | 8/9/2023 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
8/3/2023
| | 8/3/2023 | |
More Info
|
| INSULATION COMM | APPROVED |
8/3/2023
| | 8/3/2023 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
7/27/2023
| | 7/27/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/27/2023
| | 7/27/2023 | |
More Info
|
| ELECT RELEASE COMM | COMM FAILED |
7/26/2023
| | 7/26/2023 | |
More Info
|
| FLATWORK COMM | APPROVED |
7/21/2023
| | 7/21/2023 | |
More Info
|
| FLATWORK COMM | COMM FAILED |
7/19/2023
| | 7/19/2023 | |
More Info
|
| ELECT ROUGH COMM | COMM FAILED |
7/19/2023
| | 7/19/2023 | |
More Info
|
| PLUMBING FINAL | APPROVED |
7/19/2023
| | 7/19/2023 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
7/19/2023
| | 7/19/2023 | |
More Info
|
| PLUMBING FINAL | COMM FAILED |
7/18/2023
| | 7/18/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/12/2023
| | 7/12/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
7/11/2023
| | 7/11/2023 | |
More Info
|
| PLUMBING FINAL | COMM FAILED |
7/11/2023
| | 7/11/2023 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
7/10/2023
| | 7/10/2023 | |
More Info
|
| PLUMB TOP OUT COMM | COMM FAILED |
6/26/2023
| | 6/26/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
6/22/2023
| | 6/22/2023 | |
More Info
|
| LATH COMM | APPROVED |
6/22/2023
| | 6/22/2023 | |
More Info
|
| CMUWALL | APPROVED |
6/21/2023
| | 6/21/2023 | |
More Info
|
| SET 2 T-10 METER | APPROVED |
6/21/2023
| 8:00 AM | 6/21/2023 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
6/19/2023
| | 6/19/2023 | |
More Info
|
| PAVING | APPROVED |
6/19/2023
| | 6/19/2023 | |
More Info
|
| SHEATHING COMM | APPROVED |
6/19/2023
| | 6/19/2023 | |
More Info
|
| BRICKWALL TIE COMM | CANCELLED |
6/16/2023
| | 6/16/2023 | |
More Info
|
| SET 2 T-10 METER | WM NOT READY |
6/16/2023
| 7:15 AM | 6/16/2023 | |
More Info
|
| METER PAYMENT | APPROVED |
6/14/2023
| | 6/14/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
6/12/2023
| | 6/12/2023 | |
More Info
|
| PAVING | APPROVED |
6/9/2023
| | 6/9/2023 | |
More Info
|
| CMUWALL | APPROVED |
6/7/2023
| | 6/7/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
6/1/2023
| | 6/1/2023 | |
More Info
|
| FRAME COMM | APPROVED |
5/23/2023
| | 5/23/2023 | |
More Info
|
| FOOTINGS COMM | APPROVED |
5/19/2023
| | 5/19/2023 | |
More Info
|
| FIRELANE INSPECTION | APPROVED |
4/17/2023
| 9:00 AM | 4/17/2023 | |
More Info
|
| PAVING | APPROVED |
4/13/2023
| | 4/13/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
3/31/2023
| | 3/31/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
3/23/2023
| | 3/23/2023 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
3/21/2023
| | 3/21/2023 | |
More Info
|
| PLUMBING ROUGH-IN | RES FAILED |
3/21/2023
| | 3/21/2023 | |
More Info
|
| FOOTINGS COMM | APPROVED |
3/20/2023
| | 3/20/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
3/15/2023
| | 3/15/2023 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
3/14/2023
| | 3/14/2023 | |
More Info
|
| COURTESY FIRE | COMPLETED |
2/23/2023
| 1:00 PM | 2/23/2023 | |
More Info
|
There are currently no reviews on this record.