Permit Info
Short Description:
1508 SF, SALAD AND GO
Expiration Date:
4/30/2023
Parcel Info
City/State/Zip:
FRISCO, TX, 75035
Subdivision:
T & M FRISCO ADDITION (CFR)
|
| APPLICANT | Rosa Morquecho | (817)529-6888 | Rosa@roguearchitects.com | 513 Main St Ste 200 | Fort Worth, TX 76102 |
| OWNER | KROGER TEXAS LP | ()- | | | TULSA, OK 74135-4442 |
| CONTRACTOR | Bear's Contracting Group, LLC | (512)666-5248 | BWalker@bearscontractinggroup.com | 202 Walton Way, Ste. 192, PMB 201 | Cedar Park, Tx 78613 |
| ELECT. CTR. | ELITE ELECTRIC LLC | (469)358-7348 | PARGASJOHN@YAHOO.COM | 9417 GARRETT DRIVE | ROWLETT, TX 75089 |
| MECH. CTR. | Able Sheet Metal and Air dba Able Mechanical | (940)566-6406 | MHILL@ABLEMECH.COM | 6400 GREEN VALLEY CIR | AUBREY, TX 76227 |
| PLUM. CTR. | NEXT GEN PLUMBING LLC | (972)741-6262 | NEXTGENPLBG@GMAIL.COM | 1030 RILEY ROAD | WHITESBORO, TX 76273 |
|
| HEALTH FINAL 08/09/2022 DML |
$35.00
|
8/26/2022
|
| CREDIT CARD FEE |
$38.50
|
5/9/2022
|
| 2 INCH T-10 METER |
$825.00
|
5/9/2022
|
| WATER METER DEPOSIT COMMERCIAL |
$1,100.00
|
5/9/2022
|
| AUTO PROCESSING FEE |
$6.00
|
11/12/2021
|
| COMMERCIAL FEE |
$90.32
|
3/2/2022
|
| COMMERCIAL BUILDING PERMIT FEE |
$1,925.25
|
3/2/2022
|
| COMMERCIAL MECHANICAL FEE |
$105.40
|
3/2/2022
|
| COMMERCIAL NEW APPLICATION FEE |
$300.00
|
11/12/2021
|
| COMMERCIAL PLUMBING FEE |
$165.72
|
3/2/2022
|
| SEWER IMPACT FEE |
$10,714.00
|
3/2/2022
|
| THOROUGHFARE IMPACT FEE |
$19,165.00
|
3/2/2022
|
| WATER IMPACT FEE |
$12,718.00
|
3/2/2022
|
| AUTO PROCESSING FEE |
$336.63
|
3/2/2022
|
| Total Fees |
|
Charged: $47,524.82
Balance Due: $0.00
|
|
| COMM CO | APPROVED |
11/1/2022
| | 11/1/2022 | |
More Info
|
| COMM CO | TEMP CO |
10/28/2022
| | 10/28/2022 | |
More Info
|
| COMM CO | TEMP CO |
9/28/2022
| | 9/28/2022 | |
More Info
|
| COMM CO | TEMP CO |
8/30/2022
| | 8/30/2022 | |
More Info
|
| COMM CO | CANCELLED |
8/23/2022
| | 8/23/2022 | |
More Info
|
| FIRE FINAL | APPROVED |
8/22/2022
| 3:00 PM | 8/22/2022 | |
More Info
|
| COMM CO | CANCELLED |
8/16/2022
| | 8/16/2022 | |
More Info
|
| COMM CO | CANCELLED |
8/15/2022
| | 8/15/2022 | |
More Info
|
| HEALTH FINAL | APPROVED |
8/11/2022
| | 8/11/2022 | |
More Info
|
| HEALTH FINAL | COMM FAILED |
8/9/2022
| | 8/9/2022 | |
More Info
|
| COURTESY HEALTH INSP | COMPLETED |
7/7/2022
| | 7/7/2022 | |
More Info
|
| MECHANICAL FINAL | APPROVED |
7/6/2022
| | 7/6/2022 | |
More Info
|
| PLUMBING FINAL | APPROVED |
7/6/2022
| | 7/6/2022 | |
More Info
|
| COMM CO | CANCELLED |
7/5/2022
| | 7/5/2022 | |
More Info
|
| ELECT FINAL COMM | APPROVED |
7/5/2022
| | 7/5/2022 | |
More Info
|
| ELECT RELEASE COMM | APPROVED |
6/17/2022
| | 6/17/2022 | |
More Info
|
| ELECT RELEASE COMM | CANCELLED |
6/1/2022
| | 6/1/2022 | |
More Info
|
| CEILING | APPROVED |
5/27/2022
| | 5/27/2022 | |
More Info
|
| SET 1 PD METER | CANCELLED |
5/27/2022
| 11:15 AM | 5/31/2022 | |
More Info
|
| SET 2 T-10 METER | APPROVED |
5/19/2022
| | 5/19/2022 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
5/17/2022
| | 5/17/2022 | |
More Info
|
| BRICKWALL TIE COMM | APPROVED |
5/11/2022
| | 5/11/2022 | |
More Info
|
| METER PAYMENT | APPROVED |
5/9/2022
| | 5/9/2022 | |
More Info
|
| DRYWALL COMM | APPROVED |
5/2/2022
| | 5/2/2022 | |
More Info
|
| INSULATION COMM | APPROVED |
4/28/2022
| | 4/28/2022 | |
More Info
|
| PLUMB TOP OUT COMM | APPROVED |
4/26/2022
| | 4/26/2022 | |
More Info
|
| FRAME AND ELEC WALL | APPROVED |
4/25/2022
| | 4/25/2022 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
4/25/2022
| | 4/25/2022 | |
More Info
|
| PLUMB TOP OUT COMM | COMM FAILED |
4/25/2022
| | 4/25/2022 | |
More Info
|
| MECHANICAL ROUGH | APPROVED |
4/25/2022
| | 4/25/2022 | |
More Info
|
| FRAME COMM | APPROVED |
4/20/2022
| | 4/20/2022 | |
More Info
|
| SHEATHING COMM | APPROVED |
4/20/2022
| | 4/20/2022 | |
More Info
|
| PAVING | APPROVED |
4/13/2022
| | 4/13/2022 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
4/6/2022
| | 4/6/2022 | |
More Info
|
| FLATWORK COMM | APPROVED |
4/6/2022
| | 4/6/2022 | |
More Info
|
| PAVING | APPROVED |
4/6/2022
| | 4/6/2022 | |
More Info
|
| FOOTINGS COMM | APPROVED |
3/28/2022
| | 3/28/2022 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
3/28/2022
| | 3/28/2022 | |
More Info
|
| SLAB COMM | APPROVED |
3/28/2022
| | 3/28/2022 | |
More Info
|
| PIER COMM | CANCELLED |
3/28/2022
| | 3/28/2022 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
3/25/2022
| | 3/25/2022 | |
More Info
|
| FOOTINGS COMM | CANCELLED |
3/25/2022
| | 3/25/2022 | |
More Info
|
| SLAB COMM | CANCELLED |
3/25/2022
| | 3/25/2022 | |
More Info
|
| ELECT ROUGH COMM | APPROVED |
3/18/2022
| | 3/18/2022 | |
More Info
|
| GREASE TRAP | APPROVED |
3/16/2022
| | 3/16/2022 | |
More Info
|
| PLUMBING ROUGH-IN | APPROVED |
3/16/2022
| | 3/16/2022 | |
More Info
|
| PLUMBING ROUGH-IN | CANCELLED |
3/11/2022
| | 3/11/2022 | |
More Info
|
There are currently no reviews on this record.