Permit Info
Short Description:
8470 SF, ENTERPRISE AT LEGACY OFFICE BUILDING 1 (SHELL)
Expiration Date:
12/20/2023
Parcel Info
City/State/Zip:
FRISCO, TX, 75033
Subdivision:
LEGACY CROSSING
|
APPLICANT | SHOAIB MOHAMMED | (469)486-3095 | pm@perfectgc.net | 4433 Punjab Way | Frisco, TX 75033 |
OWNER | BIG D LEGACY LLC | ()- | | | FRISCO, TX 75033 |
CONTRACTOR | PERFECT GENERAL CONTRACTORS LLC | (469)536-2026 | dushyant@chaluvadi.net | 4433 PUNJAB WAY STE 301 | FRISCO, TX 75033-6747 |
ELECT. CTR. | AL FAIZ ELECTRIC | (214)796-3084 | info@alfaizelectric.com | | |
MECH. CTR. | JADCO HEATING & A/C | (972)353-2477 | JADCO@LIVE.COM | 5420 SHEPHERD PL | FLOWER MOUND, TX 75028 |
PLUM. CTR. | TRIPLE A DALLAS PLUMBING & SERVICE | (214)207-4736 | dallasplumbingservice@yahoo.com | 1715 WALL ST #102 | GARLAND, TX 75041 |
|
BRICKWALL TIE COMM 07/13/2022 CW |
$35.00
|
7/27/2022
|
INSULATION COMM 11/02/2022 CW |
$35.00
|
11/2/2022
|
PERCENT CREDIT CARD FEE |
$39.20
|
11/2/2022
|
PERCENT CREDIT CARD FEE |
$39.98
|
11/2/2022
|
2 INCH T-10 METER |
$825.00
|
11/2/2022
|
WATER METER DEPOSIT COMMERCIAL |
$1,100.00
|
11/2/2022
|
AUTO PROCESSING FEE |
$6.00
|
11/23/2021
|
COMMERCIAL FEE |
$368.80
|
12/23/2021
|
COMMERCIAL BUILDING PERMIT FEE |
$3,065.25
|
12/23/2021
|
COMMERCIAL MECHANICAL FEE |
$453.50
|
12/23/2021
|
COMMERCIAL NEW APPLICATION FEE |
$300.00
|
11/23/2021
|
COMMERCIAL PLUMBING FEE |
$792.30
|
12/23/2021
|
SEWER IMPACT FEE |
$0.00
|
|
THOROUGHFARE IMPACT FEE |
$0.00
|
|
WATER IMPACT FEE |
$0.00
|
|
AUTO PROCESSING FEE |
$0.70
|
7/27/2022
|
Total Fees |
Charged: $7,060.73
Balance Due: $0.00
|
|
BUILDING FINAL | APPROVED |
6/23/2023
| | 6/23/2023 | |
More Info
|
BUILDING FINAL | COMM FAILED |
6/19/2023
| | 6/19/2023 | |
More Info
|
FIRE FINAL | APPROVED |
5/26/2023
| 11:00 AM | 5/26/2023 | |
More Info
|
FIRE FINAL | FIRE FAILED |
5/19/2023
| 8:00 AM | 5/19/2023 | |
More Info
|
FIRE FINAL | CANCELLED |
5/8/2023
| 8:00 AM | 5/8/2023 | |
More Info
|
FIRE FINAL | FIRE FAILED |
4/20/2023
| 9:15 AM | 4/20/2023 | 10:30 AM |
More Info
|
INSPECTION ASSIST | COMPLETED |
4/20/2023
| 9:15 AM | 4/20/2023 | 10:30 AM |
More Info
|
ELECT FINAL COMM | APPROVED |
4/18/2023
| | 4/18/2023 | |
More Info
|
ELECT FINAL COMM | COMM FAILED |
4/14/2023
| | 4/14/2023 | |
More Info
|
PLUMBING FINAL | APPROVED |
4/12/2023
| | 4/12/2023 | |
More Info
|
PLUMBING FINAL | COMM FAILED |
4/11/2023
| | 4/11/2023 | |
More Info
|
MECHANICAL FINAL | APPROVED |
4/4/2023
| | 4/4/2023 | |
More Info
|
MECHANICAL ROUGH | CANCELLED |
4/3/2023
| | 4/3/2023 | |
More Info
|
PLUMBING FINAL | COMM FAILED |
4/3/2023
| | 4/3/2023 | |
More Info
|
ELECT FINAL COMM | COMM FAILED |
3/30/2023
| | 3/30/2023 | |
More Info
|
MECHANICAL ROUGH | APPROVED |
3/23/2023
| | 3/23/2023 | |
More Info
|
COURTESY FIRE | COMPLETED |
1/10/2023
| 8:00 AM | 1/11/2023 | |
More Info
|
ELECT RELEASE COMM | APPROVED |
1/4/2023
| | 1/4/2023 | |
More Info
|
SET 2 T-10 METER | APPROVED |
1/3/2023
| 8:45 AM | 1/3/2023 | |
More Info
|
ELECT RELEASE COMM | CANCELLED |
1/3/2023
| | 1/3/2023 | |
More Info
|
DRYWALL COMM | APPROVED |
11/17/2022
| | 11/17/2022 | |
More Info
|
FLATWORK COMM | APPROVED |
11/9/2022
| | 11/9/2022 | |
More Info
|
INSULATION COMM | APPROVED |
11/7/2022
| | 11/7/2022 | |
More Info
|
METER PAYMENT | APPROVED |
11/7/2022
| | 11/7/2022 | |
More Info
|
INSULATION COMM | COMM FAILED |
11/2/2022
| | 11/2/2022 | |
More Info
|
FRAME COMM | APPROVED |
10/25/2022
| | 10/25/2022 | |
More Info
|
ELECT ROUGH COMM | APPROVED |
10/5/2022
| | 10/5/2022 | |
More Info
|
PIER COMM | APPROVED |
10/4/2022
| | 10/4/2022 | |
More Info
|
PIER COMM | COMM FAILED |
9/28/2022
| | 9/28/2022 | |
More Info
|
BRICKWALL TIE COMM | APPROVED |
8/25/2022
| | 8/25/2022 | |
More Info
|
LATH COMM | APPROVED |
8/25/2022
| | 8/25/2022 | |
More Info
|
BRICKWALL TIE COMM | COMM FAILED |
7/13/2022
| | 7/13/2022 | |
More Info
|
PLUMB TOP OUT COMM | APPROVED |
7/13/2022
| | 7/13/2022 | |
More Info
|
PLUMB TOP OUT COMM | COMM FAILED |
7/8/2022
| | 7/8/2022 | |
More Info
|
SHEATHING COMM | APPROVED |
5/11/2022
| | 5/11/2022 | |
More Info
|
FIRELANE INSPECTION | APPROVED |
4/26/2022
| 9:00 AM | 4/26/2022 | |
More Info
|
SLAB COMM | APPROVED |
2/10/2022
| | 2/10/2022 | |
More Info
|
SLAB COMM | APPROVED |
1/31/2022
| | 1/31/2022 | |
More Info
|
PLUMBING ROUGH-IN | APPROVED |
1/19/2022
| | 1/19/2022 | |
More Info
|
PLUMBING ROUGH-IN | COMM FAILED |
1/18/2022
| | 1/18/2022 | |
More Info
|
There are currently no reviews on this record.