Notes:
12/22/2020 3:18:06 PM
REVISED PLANS TO REDUCE AC + GARAGE SQUARE FOOTAGE AND RELEASE FROM FIRE SPRINKLER SYSTEM REQUIREMENT
12/22/2020 3:19:02 PM
PIER DETAILS
POST-TENSION W / PIERS, SEE ENGINEERS DETAIL FOR SPEC'S ON PIER DETAIL, CABLE DETAIL, AND PLUMBING DETAIL FOR SLAB PENETRATIONS. ENGINEERS PRE-POUR INSPECTION LETTER OF ACCEPTANCE REQUIRED FOR PIERS.
***HANDRAIL HEIGHT:: R311.7.8.1 2015 IRC:: HANDRAIL SHALL NOT BE LESS THAN 34 INCHES AND NOT MORE THAN 38 INCHES.***
001. COMPLIANCE WITH THE AMENDED ZONING ORDINANCE (13-06-36) AND ALL DEED RESTRICTIONS SHOWN ON THE FINAL PLAT (DRIVEWAY; FENCE).
002. COMPLIANCE WITH THE 2015 BUILDING CODES, LOCAL AMENDMENTS, PD AND FINAL PLAT REQUIREMENTS.
003. TERMITE BARRIER PROTECTION REQ'D AT ALL SLAB PENETRATIONS.
006. MAX STRUCTURE HEIGHT FROM AVG FINISH GRADE 40'-0".
016. BEAMS=10"W X 30"D.
023. FRONT ENTRY CURB CUT PER ENCLOSED DESIGN SKETCH WITH DRIVEWAY MAXIMUM WIDTH 24 FEET.
032. ALL SIDING, TRIM, SHAKES AND SIMILAR NON-MASONRY EXTERIOR SURFACE COVERINGS MUST BE OF CEMENTITIOUS MATERIAL; (OR) ENGINEERED/TREATED WOOD PRODUCT.
034. RESIDENTIAL STUCCO REQUIRES LATH AND EXPANDED WIRE MESH WITH CEMENT PLASTER.
038. STAIR VERTICAL RISE OF 147(R311.7.3) OR GREATER REQUIRES AN INTERMEDIATE LANDING
042. TEMPERED GLASS REQUIRED AT WINDOWS AND PARTITIONS WITHIN 2' OF DOOR OPENINGS.
043. TEMPERED GLASS REQUIRED AT ALL BATHROOM HAZARD LOCATIONS, INCLUDING WINDOWS AND PARTITIONS IF GLAZING IS LESS THAN 60" ABOVE ANY STANDING/WALKING SURFACE.
044. TEMPERED GLASS AT FLOAT GLASS WINDOWS GREATER THAN 9 SQ FT, LESS THAN 18" OFF FINISH FLOOR, WITHIN 3'-0" OF A WALKING SURFACE.
045. MINIMUM OF 24" ON SILL HEIGHT AT 2ND STORY OPERABLE WINDOWS. EMERGENCY/ESCAPE RESCUE OPENINGS SHALL HAVE NET CLEAR OPENING OF GREATER THAN OR EQUAL TO 5.7 SF. MINIMUM NET CLEAR HEIGHT OF 24" AND NET CLEAR WIDTH OF 20" (GRADE FLOOR OR BELOW GREATER THAN OR EQUAL TO 5.0SF).
050. DOUBLE UNDERLAYMENT REQUIRED ON COMPOSITION ROOFS WITH A 4:12 PITCH OR LESS
051. CO DETECTORS REQ'D ON ELECTRICAL LEGEND AND ELECTRICAL PLAN. (1) PER FLOOR MINIMUM WITH (1) ON THE AC SIDE OF THE GARAGE DOOR AND OUTSIDE THE VICINITY OF EACH BEDROOM.
058. GREEN BUILDING VENTILATION REQUIREMENT BASED ON ASHARAE 62.2 STANDARD.
059. DRIVEWAY, LEAD WALK AND GARAGE DOOR ENHANCEMENT AND TREATMENT PER THE ENCLOSED DETAIL
060. THIS SUBDIVISION MAY REQUIRE H.O.A. DESIGN APPROVAL PRIOR TO PERMIT AND CONSTRUCTION.
061. SEE ENCLOSED SHEET FOR WOOD FENCE CONSTRUCTION AND (OR) ORNAMENTAL IRON AS PER PD REQUIREMENT.
2ND FLOOR:: 3BR, 2BA, GAME, MEDIA, BRIDGE, COVERED DECK.