4801 AC, 6009 SF, SFR / 2 STORY
2/21/2014 12:00:00 AM
001. COMPLIANCE WITH THE AMENDED (06/18/13) ZONING ORDINANCE.
002. COMPLIANCE WITH THE 2012 BUILDING CODES, LOCAL AMENDMENTS AND PLANNED DEVELOPMENT REQUIREMENTS.
003. TERMITE BARRIER PROTECTION REQ'D AT ALL SLAB PENETRATIONS.
005. RETAINING WALLS TWO (2) FT OR TALLER MUST BE OF ENGINEERED DESIGN.
012. BEAMS=10"W X 28"D.
021. FRONT ENTRY CURB CUT PER ENCLOSED DESIGN SKETCH WITH DRIVEWAY MAXIMUM WIDTH 24 FEET.
022. INCLUDED IN THIS PERMIT PACK IS THE REQUIRED BARRIER-FREE RAMP; USE THE APPROPRIATE DETAIL FIGURE 1 OR 1a.
036. ATTIC STORAGE MUST NOT BE CONVERTED TO HABITABLE LIVING AREA WITHOUT A BUILDING PERMIT
041. TEMPERED GLASS REQ'D AT WINDOWS AND PARTITIONS WITHIN 2' OF DOOR OPENINGS.
043. TEMPERED GLASS AT FLOAT GLASS WINDOWS GREATER THAN 9 SQ FT, LESS THAN 18" OFF FINISH FLOOR, WITHIN 3'-0" OF A WALKING SURFACE.
051. CO DETECTORS REQ'D ON ELECTRICAL LEGEND & ELECTRICAL PLAN. (1) PER FLOOR MINIMUM WITH (1) ON THE AC SIDE OF THE GARAGE DOOR AND OUTSIDE THE VICINITY OF EACH BEDROOM.
052. AUTOMATIC FIRE SPRINKLERS REQ'D W/ DESIGN & INSTALLATION APPROVED BY FIRE MARSHAL.
056. LANDSCAPE IRRIGATION SYSTEM REQUIRES DESIGN APPROVAL PRIOR TO REQUEST FOR FINAL INSPECTION (CO).
057. ET BASED CONTROLLER REQUIRED FOR AUTOMATIC IRRIGATION SYSTEMS PER CITY ORDINANCE ZA06-0005 DATED 11/24/2006.
058. GREEN BUILDING VENTILATION REQUIREMENT BASED ON ASHARAE 62.2 STANDARD.
060. THIS SUBDIVISION MAY REQUIRE H.O.A. DESIGN APPROVAL PRIOR TO PERMIT AND CONSTRUCTION.
061. SEE ENCLOSED SHEET FOR WOOD FENCE CONSTRUCTION AND (OR) ORNAMENTAL IRON AS PER PD REQUIREMENT.
(2/21/2014 10:23 AM JC)
(MFD)
(3/7/2014 3:15 PM JC)
Corrected sideyard set-back.