Notes:
3190 AC, 3790 SF, SFR / 2 STORY
3/29/2012 12:00:00 AM
002. COMPLIANCE WITH THE 2006 BUILDING CODES, AMENDMENT AND PLANNED DEVELOPMENT REQUIREMENTS.
003. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS.
007. BEAMS=8"W X 30"D.
025. TEMPERED GLASS REQ'D AT WINDOWS WITHIN 2' OF DOOR OPENINGS.
029. TEMPERED GLASS AT FLOAT GLASS WINDOWS GREATER THAN 9 SQ FT, LESS THAN 18" OFF FINISH FLOOR, WITHIN 3'-0" OF A WALKING SURFACE.
036. MINIMUM OF 24" ON SILL HEIGHT AT 2ND STORY OPERABLE WINDOWS.
040. ON "0" SET-BACK SIDE OF HOUSE NO METERS OR VENTS ARE ALLOWED. GUTTER DOWNSPOUTS MUST DISCHARGE ONTO SAME PROPERTY 5'-0" FROM FOUNDATION.
041. DOUBLE UNDERLAYMENT REQUIRED ON COMPOSITION ROOFS WITH A 4:12 PITCH OR LESS-MINIMUM PITCH 2:12.
042. THIS SUBDIVISION MAY REQUIRE H.O.A. DESIGN APPROVAL PRIOR TO PLAN SUBMITTAL AND CONSTRUCTION.
048. LANDSCAPE IRRIGATION SYSTEM, IF INSTALLED, REQUIRES DESIGN APPROVAL PRIOR TO REQUEST FOR FINAL INSPECTION (CO).
049. GREEN BUILDING VENTILATION REQUIREMENT BASED ON ASHARAE 62.2 STANDARD.
050. ET BASED CONTROLLER REQUIRED FOR AUTOMATIC IRRIGATION SYSTEMS PER CITY ORDINANCE ZA06-0005 DATED 11/24/2006.
053. SEE THE ENCLOSED ONE (1) HOUR FIREWALL DESIGN SKETCH.
054. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
060. ONLY THE EOR STRUCTURE FRAME AND DETAILS ARE INCLUDED AS PART OF TIHS ISSUED BUILDING PERMIT.