Notes:
1805 AC, 2328 SF, SFR / 1 STORY
1/17/2006 12:00:00 AM
01. ***ENERGY STAR***
02. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
03. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
12. BEAMS=10"W X 30"D.
30. 1ST FLOOR WINDOW BOX-OUTS ONLY - AREA BOX-OUTS NOT ALLOWED.
49. SAME 3RD PARTY RATER MUST DO ALL INSPECTIONS & TESTING OF SUPPLY AND EXHAUST DUCT(S) AND DAMPERS TO MEET ENERGY STAR/GREEN BLDG REQUIREMENTS..
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
54. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
59. INCLUDED IN THIS PERMIT PACK IS A DRAWING AND SPECIFICATION OF THE REQUIRED BARRIER-FREE RAMP.
(1/17/2006 16:09 JC)
100% masonry option req'd. Stucco (masonry) is req'd. at all area box-outs with brick below.