Notes:
7785 AC, 10009 SF, SFR / 2 STORY
12/8/2005 12:00:00 AM
02. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
03. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
12. BEAMS=10"W X 30"D.
20. W/12" DIA. PIERS W/(1) #5 REBAR
25. TEMPERED GLASS REQ'D AT WINDOWS WITHIN 2' OF DOOR OPENINGS.
26. TEMPERED GLASS REQ'D AT MASTER BATHTUB WINDOW.
27. TEMPERED GLASS REQ'D AT STAIR LANDING WINDOW(S).
28. TEMPERED GLASS REQ'D AT WINDOW ADJ TO STAIR.
29. TEMPERED GLASS AT FLOAT GLASS WINDOWS GREATER THAN 9 SQ FT, LESS THAN 18" OFF FINISH FLOOR, WITHIN 3'-0" OF A WALKING SURFACE.
34. EXTERIOR TRIM MUST BE CEMENT FIBER OR ENGINEERED TREATED WOOD PRODUCT.
44. CO DETECTORS REQ'D ON ELECT LEGEND & ELECT PLAN 1/1000 SQ FT & 1 PER FLOOR MIN PLUS (1) ADD'L AT GARAGE ENTRY IN AC AREA.
46. FRONT ENTRY CURB CUT PER ENCLOSED DESIGN SKETCH.
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
54. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
57. AUTOMATIC FIRE PROTECTION SPRINKLERS REQ'D W/ DESIGN & INSTALLATION APPROVED BY FIRE MARSHAL.
58. 12 SEER ALONG WITH R-6 DUCT WORK REQ'D FOR 2000 IECC COMPLIANCE IN NON ENERGY STAR/GREEN BLDG CONSTRUCTION.
1. WE RECOMMEND A FLOOR DRAIN FOR SECOND FLOOR UTILITY ROOM; A FLOOR PAN IS REQUIRED AS A MINIMUM MEASURE.
2nd FLOOR:4-BED ROOMS, 3-BATHS, 3-1/2 BATHS, GYM AND LAUNDRY.