Notes:
4102 A/C, 4912 SF, SFR / 2 STORY
4/25/2005 12:00:00 AM
02. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
03. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
10. BEAMS=10"W X 28"D.
25. TEMPERED GLASS REQ'D AT WINDOWS WITHIN 2' OF DOOR OPENINGS.
26. TEMPERED GLASS REQ'D AT MASTER BATHTUB WINDOW.
27. TEMPERED GLASS REQ'D AT STAIR LANDING WINDOW(S).
28. TEMPERED GLASS REQ'D AT WINDOW ADJ TO STAIR.
33. MEDIA ROOM WITH CLOTHES CLOSET MUST HAVE OPERABLE WINDOW.
49. SAME 3RD PARTY RATER MUST DO ALL INSPECTIONS & TESTING OF SUPPLY AND EXHAUST DUCT(S) AND DAMPERS TO MEET ENERGY STAR/GREEN BLDG REQUIREMENTS..
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
54. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
59. INCLUDED IN THIS PERMIT PACK IS A DRAWING AND SPECIFICATION OF THE REQUIRED BARRIER-FREE RAMP.