Notes:
3565 AC, 3565 SQ FT, SFR / 2 STORY
2/17/2005 12:00:00 AM
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
10. BEAMS=10"W X 28"D.
24. EXITWAYS (HALLWAYS) MUST BE A MIN. 36"W INCLUDING ARCHED OR CASED OPENINGS. (TWO OR MORE ROOMS)
25. TEMPERED GLASS REQ'D AT WINDOWS WITHIN 2' OF DOOR OPENINGS.
26. TEMPERED GLASS REQ'D AT MASTER BATHTUB WINDOW.
32. SECOND FLOOR SIDING AREA MUST NOT EXCEED 50% OF THE TOTAL NET EXPOSED WALL AREA.
33. MEDIA ROOM WITH CLOTHES CLOSET MUST HAVE OPERABLE WINDOW.
35. 2 X 6 PLUMBING (VENT STACK/WASTE)WALLS REQ'D.
44. CO DETECTORS REQ'D ON ELECT LEGEND & ELECT PLAN 1/1000 SQ FT & 1 PER FLOOR MIN PLUS (1) ADD'L AT GARAGE ENTRY IN AC AREA.
46. FRONT ENTRY CURB CUT PER ENCLOSED DESIGN SKETCH.
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
54. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
58. 12 SEER ALONG WITH R-6 DUCT WORK REQ'D FOR 2000 IECC COMPLIANCE IN NON ENERGY STAR/GREEN BLDG CONSTRUCTION.
*STUCCO BOARD NOT ACCEPTABLE...STUCCO REQUIRED ON 2ND FLOOR ELEVATION.
* 2ND LEVEL WITH 3 BDRMS, 2 BATHS, GAME ROOM AND MEDIA ROOM.