Notes:
2175 A/C, 2766 SF, SFR / 2 STORY
2/1/2005 12:00:00 AM
1. ***ENERGY STAR***
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
10. BEAMS=10"W X 28"D.
23. GARAGE MUST BE A MIN. 18'W X 20'D CLEAR SHEET ROCK TO SHEET ROCK.
38. 1 HOUR FIRE WALL ASSEMBLY REQ'D - SUBMIT DESIGN PRIOR TO WALL CONSTRUCTION.
41. TWO-HOUR FIRE SEPERATION REQUIRED.
43. SEE SOUND TRANSMISSION CODE COMPLIANCE DATA SHEET ATTACHED.
49. SAME 3RD PARTY RATER MUST DO ALL INSPECTIONS & TESTING OF SUPPLY AND EXHAUST DUCT(S) AND DAMPERS TO MEET ENERGY STAR/GREEN BLDG REQUIREMENTS..
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
54. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
57. AUTOMATIC FIRE PROTECTION SPRINKLERS REQ'D W/ DESIGN & INSTALLATION APPROVED BY FIRE MARSHAL.
* GARAGE MUST BE 18' X 20'
* 2ND LEVEL WITH 3 BDRMS, 2 BATHS, STUDY AND LAUNDRY
* PROVIDE DRAIN IN UPSTAIRS LAUNDRY