Notes:
5647 A/C, 7296 SF, SFR / 2 STORY
1/15/2005 12:00:00 AM
1. ***ENERGY STAR***
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
10. BEAMS=10"W X 28"D.
32. SECOND FLOOR SIDING AREA MUST NOT EXCEED 50% OF THE TOTAL NET EXPOSED WALL AREA.
33. MEDIA ROOM WITH CLOTHES CLOSET MUST HAVE OPERABLE WINDOW.
46. FRONT ENTRY CURB CUT PER ENCLOSED DESIGN SKETCH.
49. SAME 3RD PARTY RATER MUST DO ALL INSPECTIONS & TESTING OF SUPPLY AND EXHAUST DUCT(S) AND DAMPERS TO MEET ENERGY STAR/GREEN BLDG REQUIREMENTS..
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
54. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
57. AUTOMATIC FIRE PROTECTION SPRINKLERS REQ'D W/ DESIGN & INSTALLATION APPROVED BY FIRE MARSHAL.
(01/15/2005 11:36 JC)Driveway and drive through at Porte Cochere must be a min. width of 10'-0".