Notes:
2221 AC, 2805 SQ FT, SFR / TH/ 2 STORY
11/15/2004 12:00:00 AM
1. ***ENERGY STAR***
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
10. BEAMS=10"W X 28"D.
25. TEMPERED GLASS REQ'D AT WINDOWS WITHIN 2' OF DOOR OPENINGS.
26. TEMPERED GLASS REQ'D AT MASTER BATHTUB WINDOW.
29. TEMPERED GLASS AT FLOAT GLASS WINDOWS GREATER THAN 9 SQ FT, LESS THAN 18" OFF FINISH FLOOR, WITHIN 3'-0" OF A WALKING SURFACE.
41. TWO-HOUR FIRE SEPERATION REQUIRED.
43. SEE SOUND TRANSMISSION CODE COMPLIANCE DATA SHEET ATTACHED.
49. SAME 3RD PARTY RATER MUST DO ALL INSPECTIONS & TESTING OF SUPPLY AND EXHAUST DUCT(S) AND DAMPERS TO MEET ENERGY STAR/GREEN BLDG REQUIREMENTS..
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
57. AUTOMATIC FIRE PROTECTION SPRINKLERS REQ'D W/ DESIGN & INSTALLATION APPROVED BY FIRE MARSHAL.
(11/15/2004 08:41 JC)See Permit # B04-3619 for fire-wall reqmt's.