Notes:
3211 AC, 4317 SQ FT, SFR / 2 STORY
10/30/2004 12:00:00 AM
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
10. BEAMS=10"W X 28"D.
21. W/12" DIA. PIERS W/(2) #5 REBAR
29. TEMPERED GLASS AT FLOAT GLASS WINDOWS GREATER THAN 9 SQ FT, LESS THAN 18" OFF FINISH FLOOR, WITHIN 3'-0" OF A WALKING SURFACE.
31. SIDING OVER MASONRY AT SECOND STORY NOT ALLOWED.
34. SIDING & TRIM MUST BE CEMENT FIBER OR ENGINEERED TREATED WOOD PRODUCT.
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
51. "ASCE" REQUIRES TOP AND / OR BOTTOM BEAM REBAR PER 5.2.2.3 d.
54. PROVIDE EXPANSION JOINTS IN MASONARY FACADE.
58. 12 SEER ALONG WITH R-6 DUCT WORK REQ'D FOR 2000 IECC COMPLIANCE IN NON ENERGY STAR/GREEN BLDG CONSTRUCTION.