Notes:
4843 AC, 5659 SQ FT, SFR / 2 STORY
12/24/2003 12:00:00 AM
1. ***ENERGY STAR***
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
13. BEAMS=10"W X 32"D.
21. W/12" DIA. PIERS W/(2) #5 REBAR
26. TEMPERED GLASS REQ'D AT MASTER BATHTUB WINDOW.
27. TEMPERED GLASS REQ'D AT STAIR LANDING WINDOW(S).
33. MEDIA ROOM WITH CLOTHS CLOSET MUST HAVE OPERABLE WINDOW.
42. PROVIDE SOIL MOISTURE TREATMENT DOCUMENTATION PRIOR TO STARTING CONSTRUCTION.
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
58. 12 SEER ALONG WITH R-6 DUCT WORK REQ'D FOR 2000 IECC COMPLIANCE IN NON ENERGY STAR/GREEN BLDG CONSTRUCTION.
(12/24/2003 08:50 MBW)GRADE BEAMS-94)#5 REBAR TOP AND BOTTOM OF ALL BEAMS.