Notes:
5180 AC, 6402 SQ FT, SFR / 2 STORY
11/16/2003 12:00:00 AM
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
10. BEAMS=10"W X 28"D.
20. W/12" DIA. PIERS W/(1) #5 REBAR
24. EXITWAYS (HALLWAYS) MUST BE A MIN. 36"W INCLUDING ARCHED OR CASED OPENINGS. (TWO OR MORE ROOMS)
25. TEMPERED GLASS REQ'D AT WINDOWS WITHIN 2' OF DOOR OPENINGS.
27. TEMPERED GLASS REQ'D AT STAIR LANDING WINDOW(S).
29. TEMPERED GLASS AT FLOAT GLASS WINDOWS GREATER THAN 9 SQ FT, LESS THAN 18" OFF FINISH FLOOR, WITHIN 3'-0" OF A WALKING SURFACE.
33. MEDIA ROOM WITH STORAGE CLOSET MUST HAVE OPERABLE WINDOW.
35. 2 X 6 PLUMBING (VENT STACK/WASTE)WALLS REQ'D.
46. FRONT ENTRY CURB CUT PER ENCLOSED DESIGN SKETCH.
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
58. 12 SEER ALONG WITH R-6 DUCT WORK REQ'D FOR 2000 IECC COMPLIANCE IN NON ENERGY STAR/GREEN BLDG CONSTRUCTION.