Notes:
3728 AC, 4236 SQ FT, SFR / 2 STORY
11/10/2003 12:00:00 AM
1. ***ENERGY STAR***
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
4. BEAMS=8"W X 24"D.
8. BEAMS=10"W X 24"D.
44. CO DETECTORS REQ'D ON ELECT LEGEND & ELECT PLAN 1/1000 SQ FT & 1 PER FLOOR MIN PLUS (1) ADD'L AT GARAGE ENTRY IN AC AREA.
49. SAME 3RD PARTY RATER MUST DO ALL INSPECTIONS & TESTING OF SUPPLY AND EXHAUST DUCT(S) AND DAMPERS TO MEET ENERGY STAR/GREEN BLDG REQUIREMENTS..
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
51. "ASCE" REQUIRES TOP AND / OR BOTTOM BEAM REBAR PER 5.2.2.3 d.
(11/10/2003 11:17 MBW)BEAMS WITH (3)#5 REBAR IN TOP AND BOTTOM.