(10/29/2003 10:49 MBW)
2. COMPLIANCE WITH THE APRIL 2003 CONTRACTOR GUIDELINE REQ'D
3. TERMITE PROTECTION REQ'D AT ALL SLAB PENETRATIONS
10. BEAMS=10"W X 28"D.
21. W/12" DIA. PIERS W/(2) #5 REBAR
25. TEMPERED GLASS REQ'D AT WINDOWS WITHIN 2' OF DOOR OPENINGS.
35. 2 X 6 PLUMBING (VENT STACK/WASTE)WALLS REQ'D.
46. FRONT ENTRY CURB CUT PER ENCLOSED DESIGN SKETCH.
50. CSST GAS PIPING ALLOWED - SEE INFO SKETCH IN LOBBY AND (OR) ORDINANCE(S) 03-07-58 & 03-07-59.
58. 12 SEER ALONG WITH R-6 DUCT WORK REQ'D FOR 2000 IECC COMPLIANCE IN NON ENERGY STAR/GREEN BLDG CONSTRUCTION.
(10/29/2003 10:49 MBW)FIRST FLOOR GABLES MUST BE MASONRY(STUCCO IN PLACE OF BRICK IF DESIRED).
SECOND FLOOR WITH 3 BEDROOM, 2 BATHROOMS, MEDIA ROOM AND 10'X14' LOFT AREA AT TOP OF STAIRS.
4642 AC, 6371 SQ FT, SFR / 2 STORY