1- CONTINGENT UPON COMPLIANCE WITH ALL CODE AND CITY REQUIREMENTS.
2- CONFORM TO STATE LEGISLATION FOR SUBMITTAL OF STATEMENT OF ASBESTOS-FREE NEW CONSTRUCTION AND RECORD KEEPING OF MSDS DOCUMENTATION.
3- DUMPSTER AREA ENCLOSURE CRITERIA AND ORIENTATION TO MEET THE APPROVAL OF THE ENVIRONMENTAL SVCS DEPT. BEFORE STARTING ANY CONSTRUCTION (972-335-5519).
4- WHEN EXTERIOR WALL INSULATION IS INTENDED TO BE "BY OTHERS", SIGNS MUST BE PASTED ON THE INSIDE-SIDE OF THE EXTERIOR PANELS TO WARN INSPECTORS AND FINISH-OUT CONTRACTORS OF THE REQUIRED INSULATION YET TO BE INSTALLED.
5- ROOF DRAINAGE SYSTEM TO BE BY ROOF DRAINS PIPED INTERNALLY TO STORM DISCHARGE AS REQUIRED. SCUPPERS ARE ALLOWED FOR "OVERFLOW" PURPOSE ONLY.
6- PROVIDE 2HR WALL @ BLDG END ABUTTING THE ADJACENT BLDG AS REQUIRED.
7- SUBJECT TO FIRE MARSHAL AND FIELD INSPECTIONS.
28862 SQ FT, CNEW / SHAFER PLAZA (BLDG 'E' SHELL)