| Heading | 04/25/2024 | AST PIPE INSP | DAVID JAHN | CANCELLED | Future inspection | 4/24/2024 11:31:45 AM
Contact Name Debbie Denman
Company Name DDC Fuel Services
Email Address ddc.debbie@gmail.com
Phone Number 8174120300
Occupancy Name The Star Phase V
Occupancy Address 3965 Dallas Parkway
Is this a Re-Inspection? No
Inspection Type Above Ground Storage Tank
Assigned B, CO, or FD Permit Number FD23-00114
Any Additional Information Needed Pressure test request on Generator Aboveground Fuel Storage Tank
|
|
| Heading | 04/25/2024 | AST TANK INSP | DAVID JAHN | APPROVED | | 4/24/2024 11:31:52 AM
Contact Name Debbie Denman
Company Name DDC Fuel Services
Email Address ddc.debbie@gmail.com
Phone Number 8174120300
Occupancy Name The Star Phase V
Occupancy Address 3965 Dallas Parkway
Is this a Re-Inspection? No
Inspection Type Above Ground Storage Tank
Assigned B, CO, or FD Permit Number FD23-00114
Any Additional Information Needed Pressure test request on Generator Aboveground Fuel Storage Tank
|
|
| Heading | 05/01/2024 | AST FUEL | RUSSELL BUNGER | APPROVED | Fuel filling test | 4/30/2024 1:35:46 PM
Contact Name Brandon Jacobson
Company Name JMEG, LLC
Email Address brandon.jacobson@jmeg.us
Phone Number 715-897-3367
Occupancy Name The Star Phase V
Occupancy Address 3965 Dallas Pkwy
Is this a Re-Inspection? No
Inspection Type Above Ground Storage Fuel
Assigned B, CO, or FD Permit Number FD23-00114
Any Additional Information Needed Piping pressure test to happen before fuel fill test, please schedule for Wednesday 5/1/2024 morning
5/3/2024 4:00:03 PM
Fueling of tank, testing 90% and 95 % cutoff alarms.
|
|
| Heading | 05/01/2024 | AST PIPE INSP | RUSSELL BUNGER | APPROVED | See Report | 4/30/2024 1:35:54 PM
Contact Name Brandon Jacobson
Company Name JMEG, LLC
Email Address brandon.jacobson@jmeg.us
Phone Number 715-897-3367
Occupancy Name The Star Phase V
Occupancy Address 3965 Dallas Pkwy
Is this a Re-Inspection? No
Inspection Type Above Ground Storage Fuel
Assigned B, CO, or FD Permit Number FD23-00114
Any Additional Information Needed Piping pressure test to happen before fuel fill test, please schedule for Wednesday 5/1/2024 morning
5/3/2024 4:00:39 PM
one hour pressure test of tank and lines.
|
|
|