BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
|
APPROVED DATE: 1/30/2025
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B25-00260
|
| JOB ADDRESS: 14079 LAFERTY ST FRISCO, TX 75033 |
DESC:
4221 AC, 5227 SF, 2 STORY |
|
OWNER:
VPTM FIELDS LB LLC
901 MARQUETTE AVE STE 3300 MINNEAPOLIS MN 55402
|
CONTRACTOR:
BRITTON HOMES / PERRY HOMES CO
9000 GULF FREEWAY HOUSTON TX 77017
|
|
ISSUED DATE: 1/30/2025
APPLIED DATE:1/27/2025
EXPIRED DATE:3/18/2026
SITE APN:ADD321694
STATUS:COMPLETED
|
|
APPLICANT:
Perry Homes
3200 Southwest Fwy Suite 2800 Houston TX 77027
| |
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
| 2NDS AND FRAMING 04/28/2025 DW2 | $30.00 |
| 2NDS AND FRAMING 05/02/2025 DW2 | $30.00 |
| INSULATION RES 05/27/2025 DW2 | $30.00 |
| PERCENT CREDIT CARD FEE | $16.70 |
| PERCENT CREDIT CARD FEE | $1.80 |
| PERCENT CREDIT CARD FEE | $2.40 |
| PERCENT CREDIT CARD FEE | $2.40 |
| PERCENT CREDIT CARD FEE | $9.10 |
| 1 INCH PD METER | $685.00 |
| WATER METER DEPOSIT | $150.00 |
| AUTO PROCESSING FEE | $6.00 |
| FENCE FEE | $20.00 |
| Z-FIELDS REIMBURSEMENT FEE | $4,257.00 |
| RESIDENTIAL NEW PERMIT FEE | $1,778.10 |
| RESIDENTIAL FEE | $156.81 |
| RESIDENTIAL MECHANICAL FEE | $141.50 |
| RESIDENTIAL NEW APPLICATION FEE | $300.00 |
| RESIDENTIAL PLUMBING FEE | $249.00 |
| SEWER IMPACT FEE | $2,344.00 |
| THOROUGHFARE IMPACT FEE | $0.00 |
| WATER IMPACT FEE | $2,216.00 |
| AUTO PROCESSING FEE | $223.25 |
| BRICKWALL TIES RES 06/17/2025 RWK | $30.00 |
| ELECT FINAL RES 07/10/2025 RWK | $30.00 |
| ELECT FINAL RES 07/11/2025 RWK | $30.00 |
| FLATWORK RES 07/17/2025 RWK | $30.00 |
| DRYWALL RES 06/04/2025 RWT | $30.00 |
| PTO AND MECH ROUGH 04/14/2025 SDC | $30.00 |
| PTO AND MECH ROUGH 04/16/2025 SDC | $30.00 |
| PTO AND MECH ROUGH 04/21/2025 SDC | $30.00 |
| UTILITIES INSPECTION 08/15/2025 TL | $100.00 |
| REPLACE READABLE REGISTER 6 FT | $355.00 |
| Total Fees: | $13,344.06 |
|
|
|
| | ______ METER PAYMENT |
| ______ SET 1 PD METER |
| ______ T-POLE RES |
| ______ PLUMBING ROUGH-IN |
| ______ SLAB RES |
| ______ PTO AND MECH ROUGH |
| ______ PTO AND MECH ROUGH |
| ______ PTO AND MECH ROUGH |
| ______ PTO AND MECH ROUGH |
| ______ PTO AND MECH ROUGH |
| ______ 2NDS AND FRAMING |
| ______ 2NDS AND FRAMING |
| ______ 2NDS AND FRAMING |
| ______ 2NDS AND FRAMING |
| ______ 2NDS AND FRAMING |
| ______ INSULATION RES |
| ______ INSULATION RES |
| ______ DRYWALL RES |
| ______ DRYWALL RES |
| ______ BRICKWALL TIES RES |
| ______ BRICKWALL TIES RES |
| ______ BRICKWALL TIES RES |
| ______ PTO AND MECH ROUGH |
| ______ BRICKWALL TIES RES |
| ______ ELECT FINAL RES |
| ______ GAS RELEASE |
| ______ ELECT FINAL RES |
| ______ GAS RELEASE |
| ______ ELECT FINAL RES |
| ______ ELECT FINAL RES |
| ______ GAS RELEASE |
| ______ ELECT FINAL RES |
| ______ GAS RELEASE |
| ______ FLATWORK RES |
| ______ FLATWORK RES |
| ______ UTILITIES INSPECTION |
| ______ WATER REGISTER |
| ______ UTILITIES INSPECTION |
| ______ PLUMB MECH FINAL |
| ______ PLUMB MECH FINAL |
| ______ PLUMB MECH FINAL |
| ______ PLUMB MECH FINAL |
| ______ PLUMB MECH FINAL |
| ______ CO AND BUILD FINAL |
| ______ CO AND BUILD FINAL |
| ______ CO AND BUILD FINAL |
|
|
|
|