Seal BUILDING
Permit Payment Receipt


CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 12/3/2024 PERMIT SUB-TYPE: SNEW PERMIT NO: B24-04494
JOB ADDRESS:
14443 MALINDA DR
FRISCO, TX 75033
DESC:   4142 AC, 5111 SF, 2 STORY
OWNER:
VPTM FIELDS LB LLC
901 MARQUETTE AVE STE 3300
MINNEAPOLIS MN 55402

CONTRACTOR:
TOLL BROTHERS INC (GC)
2555 SW Grapevine Pkwy, Suite 100
Grapevine TX 76051
ISSUED DATE:
12/3/2024
APPLIED DATE:
11/19/2024
EXPIRED DATE:
3/24/2026
SITE APN:
ADD321630
STATUS:
COMPLETED
APPLICANT:
Lori Shaak
2555 SW Grapevine Pkwy #100
Grapevine TX 76051
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
0
FEE SUMMARY
INSPECTION SUMMARY
SLAB RES 02/10/2025 CMM2$30.00
2NDS AND FRAMING 05/12/2025 DW2$30.00
2NDS AND FRAMING 05/15/2025 DW2$30.00
2NDS AND FRAMING 05/22/2025 DW2$30.00
PERCENT CREDIT CARD FEE$15.10
PERCENT CREDIT CARD FEE$2.40
PERCENT CREDIT CARD FEE$2.40
PERCENT CREDIT CARD FEE$2.60
PERCENT CREDIT CARD FEE$2.60
PERCENT CREDIT CARD FEE$12.00
AUTO PROCESSING FEE$6.00
FENCE FEE$20.00
Z-FIELDS REIMBURSEMENT FEE$4,257.00
RESIDENTIAL NEW PERMIT FEE$1,743.30
RESIDENTIAL FEE$153.33
RESIDENTIAL MECHANICAL FEE$141.50
RESIDENTIAL NEW APPLICATION FEE$300.00
RESIDENTIAL PLUMBING FEE$249.00
SEWER IMPACT FEE$2,344.00
THOROUGHFARE IMPACT FEE$0.00
WATER IMPACT FEE$2,216.00
AUTO PROCESSING FEE$222.48
ELECT FINAL RES 07/17/2025 RWK$30.00
FLATWORK RES 07/28/2025 RWK$30.00
PTO AND MECH ROUGH 04/08/2025 SDC$30.00
PTO AND MECH ROUGH 04/10/2025 SDC$30.00
PTO AND MECH ROUGH 05/01/2025 SDC$30.00
PLUMB MECH FINAL 09/04/2025 SMH$30.00
UTILITIES INSPECTION 08/22/2025 TL$100.00
UTILITIES INSPECTION 08/28/2025 TL$100.00
UTILITIES INSPECTION 09/05/2025 TL$100.00
REPLACE DAMAGED/UNREADABLE REGISTER$500.00
1 INCH PD METER$605.00
WATER METER DEPOSIT$150.00
Total Fees:$13,544.71
______  METER PAYMENT
______  T-POLE RES
______  SET 1 PD METER
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB RES
______  SLAB RES
______  SHEATHING RES
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  INSULATION RES
______  DRYWALL RES
______  BRICKWALL TIES RES
______  ELECT FINAL RES
______  ELECT FINAL RES
______  FLATWORK RES
______  FLATWORK RES
______  GAS RELEASE
______  UTILITIES INSPECTION
______  UTILITIES INSPECTION
______  PLUMB MECH FINAL
______  UTILITIES INSPECTION
______  WATER REGISTER
______  PLUMB MECH FINAL
______  UTILITIES INSPECTION
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
Notes: