BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
|
APPROVED DATE: 12/9/2024
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B24-04448
|
| JOB ADDRESS: 14079 BOHANNON DR FRISCO, TX 75033 |
DESC:
4074 AC, 5085 SF, 2 STORY |
|
OWNER:
TOLL SOUTHWEST LLC
2555 SW GRAPEVINE PRKWY STE 100 GRAPEVINE TX 76051
|
CONTRACTOR:
TOLL BROTHERS INC (GC)
2555 SW Grapevine Pkwy, Suite 100 Grapevine TX 76051
|
|
ISSUED DATE: 12/9/2024
APPLIED DATE:11/14/2024
EXPIRED DATE:3/11/2026
SITE APN:ADD322118
STATUS:COMPLETED
|
|
APPLICANT:
Lori Shaak
2555 SW Grapevine Pkwy #100 Grapevine TX 76051
| |
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
| 2NDS AND FRAMING 03/26/2025 CMM2 | $30.00 |
| 2NDS AND FRAMING 04/01/2025 DW2 | $30.00 |
| 2NDS AND FRAMING 04/03/2025 DW2 | $30.00 |
| ELECT FINAL RES 05/28/2025 DW2 | $30.00 |
| PERCENT CREDIT CARD FEE | $15.10 |
| PERCENT CREDIT CARD FEE | $2.40 |
| PERCENT CREDIT CARD FEE | $2.40 |
| PERCENT CREDIT CARD FEE | $1.20 |
| 1 INCH PD METER | $605.00 |
| WATER METER DEPOSIT | $150.00 |
| T-POLE RES 12/12/2024 LUN | $30.00 |
| SLAB RES 01/27/2025 LUN | $30.00 |
| PLUMBING ROUGH-IN 01/08/2025 MLM | $30.00 |
| AUTO PROCESSING FEE | $6.00 |
| FENCE FEE | $20.00 |
| Z-FIELDS REIMBURSEMENT FEE | $4,257.00 |
| RESIDENTIAL NEW PERMIT FEE | $1,735.50 |
| RESIDENTIAL FEE | $152.55 |
| RESIDENTIAL MECHANICAL FEE | $135.00 |
| RESIDENTIAL NEW APPLICATION FEE | $300.00 |
| RESIDENTIAL PLUMBING FEE | $228.00 |
| SEWER IMPACT FEE | $2,344.00 |
| THOROUGHFARE IMPACT FEE | $0.00 |
| WATER IMPACT FEE | $2,216.00 |
| AUTO PROCESSING FEE | $221.76 |
| ELECT FINAL RES 05/20/2025 PJF | $30.00 |
| PTO AND MECH ROUGH 03/13/2025 SDC | $30.00 |
| PLUMB MECH FINAL 08/08/2025 SMH | $30.00 |
| Total Fees: | $12,691.91 |
|
|
|
| | ______ METER PAYMENT |
| ______ T-POLE RES |
| ______ SET 1 PD METER |
| ______ PLUMBING ROUGH-IN |
| ______ PLUMBING ROUGH-IN |
| ______ PLUMBING ROUGH-IN |
| ______ SLAB RES |
| ______ T-POLE RES |
| ______ SLAB RES |
| ______ SHEATHING RES |
| ______ SHEATHING RES |
| ______ PTO AND MECH ROUGH |
| ______ PTO AND MECH ROUGH |
| ______ 2NDS AND FRAMING |
| ______ 2NDS AND FRAMING |
| ______ 2NDS AND FRAMING |
| ______ 2NDS AND FRAMING |
| ______ INSULATION RES |
| ______ LATH RES |
| ______ DRYWALL RES |
| ______ ELECT FINAL RES |
| ______ ELECT FINAL RES |
| ______ ELECT FINAL RES |
| ______ ELECT FINAL RES |
| ______ FLATWORK RES |
| ______ FLATWORK RES |
| ______ FLATWORK RES |
| ______ GAS RELEASE |
| ______ PLUMB MECH FINAL |
| ______ UTILITIES INSPECTION |
| ______ PLUMB MECH FINAL |
| ______ CO AND BUILD FINAL |
|
|
|
|