BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 8/29/2024
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B24-02840
|
JOB ADDRESS: 3370 FULMAR CIR FRISCO, TX 75033 |
DESC:
3860 AC, 4665 SF, 2 STORY |
|
OWNER:
VPTM FIELDS LB LLC
901 MARQUETTE AVE STE 3300 MINNEAPOLIS MN 55402
|
CONTRACTOR:
BRITTON HOMES / PERRY HOMES CO
9000 GULF FREEWAY HOUSTON TX 77017
|
ISSUED DATE: 8/29/2024
APPLIED DATE:7/29/2024
EXPIRED DATE:8/20/2025
SITE APN:ADD321656
STATUS:COMPLETED
|
|
APPLICANT:
Austin Cornett
9000 Gulf Freeway Houston TX 77017
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
PERCENT CREDIT CARD FEE | $15.10 |
PERCENT CREDIT CARD FEE | $2.40 |
PERCENT CREDIT CARD FEE | $2.40 |
PERCENT CREDIT CARD FEE | $12.00 |
REPLACE DAMAGED/UNREADABLE REGISTER | $500.00 |
1 INCH PD METER | $605.00 |
WATER METER DEPOSIT | $150.00 |
DRYWALL RES 12/06/2024 LUN | $30.00 |
ELECT FINAL RES 01/22/2025 LUN | $30.00 |
FLATWORK RES 01/23/2025 LUN | $30.00 |
GAS RELEASE 01/17/2025 MLM | $30.00 |
PLAN REVIEW FEE | $50.00 |
AUTO PROCESSING FEE | $6.00 |
FENCE FEE | $20.00 |
Z-FIELDS REIMBURSEMENT FEE | $4,257.00 |
RESIDENTIAL NEW PERMIT FEE | $1,606.15 |
RESIDENTIAL FEE | $139.95 |
RESIDENTIAL MECHANICAL FEE | $135.00 |
RESIDENTIAL NEW APPLICATION FEE | $300.00 |
RESIDENTIAL PLUMBING FEE | $235.00 |
SEWER IMPACT FEE | $2,344.00 |
THOROUGHFARE IMPACT FEE | $0.00 |
WATER IMPACT FEE | $2,216.00 |
AUTO PROCESSING FEE | $220.06 |
PLUMBING ROUGH-IN 09/30/2024 SME2 | $30.00 |
PTO AND MECH ROUGH 11/12/2024 SME2 | $30.00 |
PTO AND MECH ROUGH 11/14/2024 SME2 | $30.00 |
PTO AND MECH ROUGH 11/18/2024 SMH | $30.00 |
UTILITIES INSPECTION 02/06/2025 TL | $100.00 |
Total Fees: | $13,156.06 |
|
|
| ______ METER PAYMENT |
______ T-POLE RES |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB RES |
______ SHEATHING RES |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ LATH RES |
______ DRYWALL RES |
______ DRYWALL RES |
______ BRICKWALL TIES RES |
______ GAS RELEASE |
______ GAS RELEASE |
______ GAS RELEASE |
______ ELECT FINAL RES |
______ FLATWORK RES |
______ GAS RELEASE |
______ ELECT FINAL RES |
______ FLATWORK RES |
______ WATER REGISTER |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ CO AND BUILD FINAL |
|
|
|