BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 5/28/2024
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B24-01545
|
JOB ADDRESS: 14008 LUCINDA PL FRISCO, 75033 |
DESC:
4046 AC, 4046 SF, 2 STORY |
|
|
CONTRACTOR:
HUNTINGTON HOMES
5601 DEMOCRACY, SUITE 300 PLANO TX 75024
|
ISSUED DATE: 5/28/2024
APPLIED DATE:4/24/2024
EXPIRED DATE:9/10/2025
SITE APN:ADD322113
STATUS:COMPLETED
|
|
APPLICANT:
Dustin Nichols
5601 Democracy Drive Plano TX 75024
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
CO AND BUILD FINAL 03/14/2025 CMM2 | $30.00 |
PERCENT CREDIT CARD FEE | $2.40 |
PERCENT CREDIT CARD FEE | $3.80 |
PERCENT CREDIT CARD FEE | $0.60 |
2NDS AND FRAMING 09/11/2024 GLQ | $30.00 |
2NDS AND FRAMING 09/12/2024 GLQ | $30.00 |
PTO AND MECH ROUGH 08/28/2024 JWR | $30.00 |
PTO AND MECH ROUGH 08/30/2024 JWR | $30.00 |
PTO AND MECH ROUGH 09/05/2024 JWR | $30.00 |
ELECT FINAL RES 12/16/2024 LUN | $30.00 |
ELECT FINAL RES 12/18/2024 LUN | $30.00 |
UTILITIES INSPECTION 01/15/2025 NMN | $100.00 |
AUTO PROCESSING FEE | $6.00 |
FENCE FEE | $20.00 |
Z-FIELDS REIMBURSEMENT FEE | $4,257.00 |
RESIDENTIAL NEW PERMIT FEE | $1,827.00 |
RESIDENTIAL FEE | $161.70 |
RESIDENTIAL MECHANICAL FEE | $148.00 |
RESIDENTIAL NEW APPLICATION FEE | $300.00 |
RESIDENTIAL PLUMBING FEE | $269.00 |
SEWER IMPACT FEE | $2,344.00 |
THOROUGHFARE IMPACT FEE | $0.00 |
WATER IMPACT FEE | $2,216.00 |
PLAN REVIEW FEE | $50.00 |
1 INCH PD METER | $605.00 |
WATER METER DEPOSIT | $150.00 |
Total Fees: | $12,700.50 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ SLAB RES |
______ SLAB RES |
______ T-POLE RES |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ DRYWALL RES |
______ BRICKWALL TIES RES |
______ FLATWORK RES |
______ FLATWORK RES |
______ ELECT FINAL RES |
______ GAS RELEASE |
______ ELECT FINAL RES |
______ GAS RELEASE |
______ ELECT FINAL RES |
______ GAS RELEASE |
______ UTILITIES INSPECTION |
______ UTILITIES INSPECTION |
______ PTO AND MECH ROUGH |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ FLATWORK RES |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
|
|
|