Seal BUILDING
Permit Payment Receipt


CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 2/7/2024 PERMIT SUB-TYPE: SNEW PERMIT NO: B24-00407
JOB ADDRESS:
13627 DALEWOOD MEWS
FRISCO, TX 75033
DESC:   2544 AC, 3067 SF, 2 STORY
OWNER:
FHQ HOLDINGS LP
1900 N AKARD ST
DALLAS TX 75201

CONTRACTOR:
TAYLOR MORRISON
6735 SALT CEDAR WAY, BLDG 1, STE 200
FRISCO TX 75034
ISSUED DATE:
2/7/2024
APPLIED DATE:
2/1/2024
EXPIRED DATE:
8/9/2025
SITE APN:
ADD314429
STATUS:
COMPLETED
APPLICANT:
Dallas Starts
6735 Salt Cedar Way
Frisco TX 75034
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
0
FEE SUMMARY
INSPECTION SUMMARY
CO AND BUILD FINAL 02/04/2025 CMM2$30.00
PERCENT CREDIT CARD FEE$15.10
PERCENT CREDIT CARD FEE$1.20
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$2.00
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$2.00
PERCENT CREDIT CARD FEE$12.00
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$0.60
2NDS AND FRAMING 09/17/2024 GLQ$30.00
SHEATHING RES 06/26/2024 RWT$30.00
ELECT FINAL RES 12/04/2024 LUN$30.00
ELECT FINAL RES 12/10/2024 LUN$30.00
UTILITIES INSPECTION 11/26/2024 NMN$100.00
REPLACE DAMAGED/UNREADABLE REGISTER$500.00
AUTO PROCESSING FEE$6.00
FENCE FEE$20.00
Z-FIELDS REIMBURSEMENT FEE$4,257.00
RESIDENTIAL NEW PERMIT FEE$1,082.78
RESIDENTIAL FEE$92.01
RESIDENTIAL MECHANICAL FEE$122.00
RESIDENTIAL NEW APPLICATION FEE$300.00
RESIDENTIAL PLUMBING FEE$164.00
SEWER IMPACT FEE$2,344.00
THOROUGHFARE IMPACT FEE$0.00
WATER IMPACT FEE$2,216.00
AUTO PROCESSING FEE$205.96
PTO AND MECH ROUGH 06/21/2024 SME2$30.00
PTO AND MECH ROUGH 08/13/2024 SMH$30.00
UTILITIES INSPECTION 09/11/2024 TL$100.00
UTILITIES INSPECTION 11/15/2024 TL$100.00
1 INCH PD METER$605.00
WATER METER DEPOSIT$150.00
Total Fees:$12,610.05
______  METER PAYMENT
______  SET 1 PD METER
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  T-POLE RES
______  SLAB RES
______  SLAB RES
______  PTO AND MECH ROUGH
______  SHEATHING RES
______  SHEATHING RES
______  PTO AND MECH ROUGH
______  SHEATHING RES
______  PTO AND MECH ROUGH
______  PLUMBING ROUGH-IN
______  UTILITIES INSPECTION
______  PTO AND MECH ROUGH
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  INSULATION RES
______  LATH RES
______  DRYWALL RES
______  FLATWORK RES
______  UTILITIES INSPECTION
______  GAS RELEASE
______  ELECT FINAL RES
______  UTILITIES INSPECTION
______  ELECT FINAL RES
______  WATER REGISTER
______  UTILITIES INSPECTION
______  ELECT FINAL RES
______  ELECT FINAL RES
______  ELECT FINAL RES
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
______  FLATWORK RES
______  CO AND BUILD FINAL
Notes: