APPROVED DATE: 2/1/2024 PERMIT SUB-TYPE: SNEW PERMIT NO: B24-00272
JOB ADDRESS:
13614 COLONY MEWS
FRISCO, TX 75033
DESC:   2524 AC, 3376 SF, 2 STORY
OWNER:
FHQ HOLDINGS LP
1900 N AKARD ST
DALLAS TX 75201

CONTRACTOR:
TAYLOR MORRISON
6735 SALT CEDAR WAY, BLDG 1, STE 200
FRISCO TX 75034
ISSUED DATE:
2/1/2024
APPLIED DATE:
1/23/2024
EXPIRED DATE:
4/29/2025
SITE APN:
ADD322637
STATUS:
COMPLETED
APPLICANT:
Dallas Starts
6735 Salt Cedar Way
Frisco TX 75034
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
0
FEE SUMMARY
INSPECTION SUMMARY
PERCENT CREDIT CARD FEE$15.10
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$2.00
PERCENT CREDIT CARD FEE$9.10
PERCENT CREDIT CARD FEE$0.60
INSULATION RES 05/30/2024 GLQ$30.00
ELECT FINAL RES 08/19/2024 GLQ$30.00
SHEATHING RES 04/25/2024 JR2$30.00
GAS RELEASE 08/30/2024 JWR$30.00
AUTO PROCESSING FEE$6.00
FENCE FEE$20.00
Z-FIELDS REIMBURSEMENT FEE$4,257.00
RESIDENTIAL NEW PERMIT FEE$1,187.84
RESIDENTIAL FEE$101.28
RESIDENTIAL MECHANICAL FEE$122.00
RESIDENTIAL NEW APPLICATION FEE$300.00
RESIDENTIAL PLUMBING FEE$163.00
SEWER IMPACT FEE$2,344.00
THOROUGHFARE IMPACT FEE$0.00
WATER IMPACT FEE$2,216.00
AUTO PROCESSING FEE$208.22
ELECT FINAL RES 08/14/2024 PJF$30.00
ELECT FINAL RES 07/24/2024 RWT$30.00
PLUMB MECH FINAL 10/21/2024 SMH$30.00
UTILITIES INSPECTION 10/01/2024 TL$100.00
UTILITIES INSPECTION 10/10/2024 TL$100.00
REPLACE READABLE REGISTER$355.00
1 INCH PD METER$605.00
WATER METER DEPOSIT$150.00
Total Fees:$12,475.74
______  METER PAYMENT
______  T-POLE RES
______  SET 1 PD METER
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB RES
______  SLAB RES
______  SLAB RES
______  PTO AND MECH ROUGH
______  SHEATHING RES
______  SHEATHING RES
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  INSULATION RES
______  PTO AND MECH ROUGH
______  BRICKWALL TIES RES
______  PTO AND MECH ROUGH
______  INSULATION RES
______  INSULATION RES
______  DRYWALL RES
______  FLATWORK RES
______  ELECT FINAL RES
______  GAS RELEASE
______  ELECT FINAL RES
______  ELECT FINAL RES
______  ELECT FINAL RES
______  ELECT FINAL RES
______  GAS RELEASE
______  GAS RELEASE
______  GAS RELEASE
______  UTILITIES INSPECTION
______  UTILITIES INSPECTION
______  UTILITIES INSPECTION
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
Notes: