BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
|
APPROVED DATE: 1/2/2024
|
PERMIT SUB-TYPE: CIFO
|
PERMIT NO: B23-04647
|
| JOB ADDRESS: 12455 ELDORADO PKWY 260 FRISCO, TX 75035 |
DESC:
1053 SF, AMBREEN'S SALON |
|
OWNER:
ELDORADO RETAIL LLC COIT
3889 MAPLE AVE STE 200 DALLAS TX 75219-3916
|
CONTRACTOR:
SKYLINE REMODELERS LLC
3905 KITE MEADOW DR Plano TX 75074
|
|
ISSUED DATE: 1/2/2024
APPLIED DATE:11/17/2023
EXPIRED DATE:3/5/2025
SITE APN:ADD314512
STATUS:COMPLETED
|
|
APPLICANT:
Duncan Kim
2695 Villa Creek Dr #110, Dallas TX 75234
| |
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 100000
|
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
| INSULATION COMM 03/27/2024 CW | $35.00 |
| CEILING 04/12/2024 CW | $35.00 |
| CEILING 05/03/2024 CW | $35.00 |
| CEILING 05/13/2024 CW | $35.00 |
| INSULATION COMM 05/16/2024 CW | $35.00 |
| CEILING 05/16/2024 CW | $35.00 |
| COMM CO 06/07/2024 CW | $35.00 |
| ELECT RELEASE COMM 06/17/2024 CW | $35.00 |
| ELECT RELEASE COMM 06/19/2024 CW | $35.00 |
| COMM CO 07/12/2024 CW | $35.00 |
| PERCENT CREDIT CARD FEE | $0.70 |
| PERCENT CREDIT CARD FEE | $1.40 |
| PERCENT CREDIT CARD FEE | $4.20 |
| PERCENT CREDIT CARD FEE | $0.70 |
| PERCENT CREDIT CARD FEE | $2.80 |
| PERCENT CREDIT CARD FEE | $1.40 |
| COMM BUILDING PERMIT FEE | $50.00 |
| ELECT FINAL COMM 07/05/2024 JDSM | $35.00 |
| PLUMBING FINAL 06/19/2024 JWR | $35.00 |
| PLUMBING FINAL 06/21/2024 JWR | $35.00 |
| MECHANICAL ROUGH 02/16/2024 MLM | $35.00 |
| PLUMB TOP OUT COMM 03/07/2024 MLM | $35.00 |
| AUTO PROCESSING FEE | $3.00 |
| COMMERCIAL FEE | $72.12 |
| COMMERCIAL MECHANICAL FEE | $82.65 |
| COMMERCIAL PLUMBING FEE | $124.77 |
| COMMERCIAL RENOVATION APPLICATION FEE | $150.00 |
| COMMERCIAL RENOVATION FEE | $446.25 |
| AUTO PROCESSING FEE | $14.52 |
| AUTO PROCESSING FEE | $1.00 |
| PLUMB TOP OUT COMM 03/11/2024 SMH | $35.00 |
| Total Fees: | $1,515.51 |
|
|
|
| | ______ FRAME COMM |
| ______ FRAME COMM |
| ______ PLUMBING ROUGH-IN |
| ______ PLUMBING ROUGH-IN |
| ______ SLAB COMM |
| ______ SLAB COMM |
| ______ FRAME AND ELEC WALL |
| ______ MECHANICAL ROUGH |
| ______ FRAME AND ELEC WALL |
| ______ MECHANICAL ROUGH |
| ______ PLUMB TOP OUT COMM |
| ______ PLUMB TOP OUT COMM |
| ______ INSULATION COMM |
| ______ CEILING |
| ______ PLUMB TOP OUT COMM |
| ______ PLUMB TOP OUT COMM |
| ______ CEILING |
| ______ PLUMB TOP OUT COMM |
| ______ CEILING |
| ______ CEILING |
| ______ CEILING |
| ______ INSULATION COMM |
| ______ CEILING |
| ______ CEILING |
| ______ PLUMBING FINAL |
| ______ PLUMBING FINAL |
| ______ ELECT FINAL COMM |
| ______ MECHANICAL FINAL |
| ______ COMM CO |
| ______ ELECT RELEASE COMM |
| ______ PLUMBING FINAL |
| ______ ELECT RELEASE COMM |
| ______ ELECT RELEASE COMM |
| ______ PLUMBING FINAL |
| ______ ELECT RELEASE COMM |
| ______ ELECT RELEASE COMM |
| ______ PLUMBING FINAL |
| ______ ELECT FINAL COMM |
| ______ PLUMBING FINAL |
| ______ ELECT FINAL COMM |
| ______ MECHANICAL FINAL |
| ______ COMM CO |
| ______ FIRE FINAL |
| ______ FIRE FINAL |
| ______ COMM CO |
| ______ COMM CO |
| ______ COMM CO |
|
|
|
|