BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
|
APPROVED DATE: 3/24/2024
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B23-04599
|
| JOB ADDRESS: 9565 SPEAKER DR FRISCO, TX 75035 |
DESC:
2262 AC, 2894 SF, 2 STORY |
|
OWNER:
JENI 2020 LLC CB
5501 HEADQUARTERS DR STE 300W PLANO TX 75024-6192
|
CONTRACTOR:
CB JENI 2020 LLC
2805 DALLAS PARKWAY PLANO TX 75093
|
|
ISSUED DATE: 3/24/2024
APPLIED DATE:11/20/2023
EXPIRED DATE:9/20/2024
SITE APN:ADD326345
STATUS:COMPLETED
|
|
APPLICANT:
CB Jeni Homes
2805 Dallas Pkwy Plano TX 75093
| |
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
| SHEATHING RES 06/10/2024 CMM2 | $30.00 |
| INSULATION RES 07/15/2024 CMM2 | $30.00 |
| 2NDS AND FRAMING 06/26/2024 DP2 | $30.00 |
| FLATWORK RES 08/12/2024 DW2 | $30.00 |
| FLATWORK RES 08/13/2024 DW2 | $30.00 |
| ELECT FINAL RES 08/21/2024 DW2 | $30.00 |
| PERCENT CREDIT CARD FEE | $15.10 |
| PERCENT CREDIT CARD FEE | $0.60 |
| PERCENT CREDIT CARD FEE | $0.60 |
| PERCENT CREDIT CARD FEE | $0.60 |
| PERCENT CREDIT CARD FEE | $1.20 |
| PERCENT CREDIT CARD FEE | $0.60 |
| PERCENT CREDIT CARD FEE | $2.00 |
| UTILITIES INSPECTION 09/04/2024 NMN | $100.00 |
| AUTO PROCESSING FEE | $6.00 |
| FENCE FEE | $20.00 |
| Z-FIELDS REIMBURSEMENT FEE | $0.00 |
| RESIDENTIAL NEW PERMIT FEE | $1,022.90 |
| RESIDENTIAL FEE | $86.82 |
| RESIDENTIAL MECHANICAL FEE | $122.00 |
| RESIDENTIAL NEW APPLICATION FEE | $300.00 |
| RESIDENTIAL PLUMBING FEE | $162.00 |
| SEWER IMPACT FEE | $2,344.00 |
| THOROUGHFARE IMPACT FEE | $0.00 |
| WATER IMPACT FEE | $2,200.00 |
| 1 INCH PD METER | $605.00 |
| WATER METER DEPOSIT | $150.00 |
| Total Fees: | $7,319.42 |
|
|
|
| | ______ METER PAYMENT |
| ______ SET 1 PD METER |
| ______ T-POLE RES |
| ______ PLUMBING ROUGH-IN |
| ______ SLAB RES |
| ______ FIRE RATED WALL RES |
| ______ SHEATHING RES |
| ______ SHEATHING RES |
| ______ PTO AND MECH ROUGH |
| ______ 2NDS AND FRAMING |
| ______ 2NDS AND FRAMING |
| ______ INSULATION RES |
| ______ INSULATION RES |
| ______ DRYWALL RES |
| ______ FLATWORK RES |
| ______ FLATWORK RES |
| ______ FLATWORK RES |
| ______ ELECT FINAL RES |
| ______ GAS RELEASE |
| ______ ELECT FINAL RES |
| ______ ELECT FINAL RES |
| ______ UTILITIES INSPECTION |
| ______ PLUMB MECH FINAL |
| ______ PLUMB MECH FINAL |
| ______ UTILITIES INSPECTION |
| ______ CO AND BUILD FINAL |
| ______ CO AND BUILD FINAL |
|
|
|
|