BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 9/28/2023
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B23-03195
|
JOB ADDRESS: 11948 DAHLIA BAY DR FRISCO, TX 75033 |
DESC:
2274 AC, 2889 SF, 2 STORY |
|
OWNER:
CLH20 LLC
150 TURTLE CREEK BLVD STE 103C DALLAS TX 75207
|
CONTRACTOR:
CLH20 LLC
4300 MacArthur Ave, Suite 165 Dallas TX 75209
|
ISSUED DATE: 9/28/2023
APPLIED DATE:8/17/2023
EXPIRED DATE:3/16/2025
SITE APN:ADD294786
STATUS:COMPLETED
|
|
APPLICANT:
Lareina Cheung
4300 MacArthur Ave, Suite 165 Dallas TX 75209
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
PLAN REVIEW FEE | $50.00 |
SLAB RES 01/18/2024 DW2 | $30.00 |
ELECT FINAL RES 07/10/2024 DW2 | $30.00 |
PERCENT CREDIT CARD FEE | $14.00 |
PERCENT CREDIT CARD FEE | $1.20 |
PERCENT CREDIT CARD FEE | $12.70 |
PERCENT CREDIT CARD FEE | $1.20 |
METER FREEZE BURST | $605.00 |
1 INCH PD METER | $540.00 |
WATER METER DEPOSIT | $150.00 |
REPLACEMENT CARD FEE | $10.00 |
GAS RELEASE 07/11/2024 JR2 | $30.00 |
AUTO PROCESSING FEE | $6.00 |
FENCE FEE | $20.00 |
Z-FIELDS REIMBURSEMENT FEE | $0.00 |
RESIDENTIAL NEW PERMIT FEE | $1,021.15 |
RESIDENTIAL FEE | $86.67 |
RESIDENTIAL MECHANICAL FEE | $122.00 |
RESIDENTIAL NEW APPLICATION FEE | $300.00 |
RESIDENTIAL PLUMBING FEE | $156.00 |
SEWER IMPACT FEE | $1,521.00 |
THOROUGHFARE IMPACT FEE | $3,042.00 |
WATER IMPACT FEE | $1,521.00 |
AUTO PROCESSING FEE | $150.80 |
SHEATHING RES 03/27/2024 RWK | $30.00 |
2NDS AND FRAMING 04/16/2024 RWK | $30.00 |
Total Fees: | $9,480.72 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ T-POLE RES |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB RES |
______ SLAB RES |
______ FIRE RATED WALL RES |
______ FIRE RATED WALL RES |
______ FIRE RATED WALL RES |
______ FIRE RATED WALL RES |
______ SHEATHING RES |
______ SHEATHING RES |
______ REPL 1 PD METER |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ BRICKWALL TIES RES |
______ INSULATION RES |
______ DRYWALL RES |
______ DRYWALL RES |
______ LATH RES |
______ FLATWORK RES |
______ ELECT FINAL RES |
______ GAS RELEASE |
______ ELECT FINAL RES |
______ GAS RELEASE |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
|
|
|