APPROVED DATE: 8/30/2023 PERMIT SUB-TYPE: SNEW PERMIT NO: B23-03185
JOB ADDRESS:
15579 CORMORANT ST
FRISCO, TX 75035
DESC:   2471 AC, 3051 SF, 2 STORY
OWNER:
FM 3537 LLC NASH
733 8TH AVE
SAN DIEGO CA 92101-6407

CONTRACTOR:
AMERICAN LEGEND HOMES
2540 KING ARTHUR BLVD
LEWISVILLE TX 75056
ISSUED DATE:
8/30/2023
APPLIED DATE:
8/16/2023
EXPIRED DATE:
8/19/2024
SITE APN:
ADD280659
STATUS:
COMPLETED
APPLICANT:
Liliana Moton
4400 State Highway 121
Lewisville TX 75056
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
0
FEE SUMMARY
INSPECTION SUMMARY
1 INCH PD METER$540.00
WATER METER DEPOSIT$150.00
PERCENT CREDIT CARD FEE$0.60
PERCENT CREDIT CARD FEE$1.80
PERCENT CREDIT CARD FEE$1.20
2NDS AND FRAMING 11/01/2023 GLQ$30.00
2NDS AND FRAMING 10/26/2023 JDR$30.00
DRYWALL RES 11/21/2023 JDR$30.00
ELECT FINAL RES 12/28/2023 JDR$30.00
ELECT FINAL RES 12/29/2023 JDR$30.00
PLUMB MECH FINAL 02/13/2024 MLM$30.00
ELECT FINAL RES 01/08/2024 PJF$30.00
T-POLE RES 08/31/2023 RWT$30.00
PLUMBING ROUGH-IN 09/08/2023 SDC$30.00
PLUMB MECH FINAL 01/30/2024 SMH$30.00
WATER IMPACT FEE$2,120.00
THOROUGHFARE IMPACT FEE$1,337.00
SEWER IMPACT FEE$0.00
RESIDENTIAL PLUMBING FEE$164.00
RESIDENTIAL NEW APPLICATION FEE$300.00
RESIDENTIAL MECHANICAL FEE$122.00
RESIDENTIAL FEE$91.53
RESIDENTIAL NEW PERMIT FEE$1,077.34
Z-FIELDS REIMBURSEMENT FEE$0.00
FENCE FEE$20.00
AUTO PROCESSING FEE$6.00
PERCENT CREDIT CARD FEE$1.20
PERCENT CREDIT CARD FEE$1.20
Total Fees:$6,233.87
______  SET 1 PD METER
______  T-POLE RES
______  T-POLE RES
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB RES
______  SLAB RES
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  BRICKWALL TIES RES
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  INSULATION RES
______  DRYWALL RES
______  DRYWALL RES
______  DRYWALL RES
______  2NDS AND FRAMING
______  FLATWORK RES
______  ELECT FINAL RES
______  GAS RELEASE
______  ELECT FINAL RES
______  ELECT FINAL RES
______  ELECT FINAL RES
______  UTILITIES INSPECTION
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
______  METER PAYMENT
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)

(THIS IS A BASIC PERMIT VIEW ONLY)