BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 6/9/2023
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B23-02171
|
JOB ADDRESS: 11477 AUTUMN BREEZE DR FRISCO, TX 75035 |
DESC:
4284 AC, 5399 SF, 2 STORY |
|
OWNER:
TEXAS HOMES INC FIRST
12089 HICKORY KNOLL LN FRISCO TX 75035-5648
|
CONTRACTOR:
FIRST TEXAS CUSTOM HOMES
500 CRESCENT CT STE 350 DALLAS TX 75201
|
ISSUED DATE: 6/9/2023
APPLIED DATE:6/1/2023
EXPIRED DATE:8/27/2024
SITE APN:ADD279903
STATUS:COMPLETED
|
|
APPLICANT:
Ana Gutierrez
500 Crescent Court, Suite 350 Dallas TX 75201
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
DRYWALL RES 10/02/2023 CMM2 | $30.00 |
DRYWALL RES 10/03/2023 CMM2 | $30.00 |
ELECT FINAL RES 11/14/2023 CMM2 | $30.00 |
ELECT FINAL RES 11/16/2023 CMM2 | $30.00 |
ELECT FINAL RES 11/21/2023 CMM2 | $30.00 |
PERCENT CREDIT CARD FEE | $2.00 |
PERCENT CREDIT CARD FEE | $1.20 |
PERCENT CREDIT CARD FEE | $0.60 |
PERCENT CREDIT CARD FEE | $0.60 |
PERCENT CREDIT CARD FEE | $1.20 |
PERCENT CREDIT CARD FEE | $1.80 |
PERCENT CREDIT CARD FEE | $1.20 |
PERCENT CREDIT CARD FEE | $0.60 |
PERCENT CREDIT CARD FEE | $2.00 |
PERCENT CREDIT CARD FEE | $0.60 |
2NDS AND FRAMING 08/29/2023 GLQ | $30.00 |
1 INCH PD METER | $540.00 |
WATER METER DEPOSIT | $150.00 |
2NDS AND FRAMING 08/24/2023 JDR | $30.00 |
2NDS AND FRAMING 09/18/2023 JDR | $30.00 |
INSULATION RES 09/18/2023 JDR | $30.00 |
INSULATION RES 09/25/2023 JDR | $30.00 |
SET 1 PD METER 06/21/2023 BCB | $100.00 |
PLUMB MECH FINAL 01/09/2024 MLM | $30.00 |
AUTO PROCESSING FEE | $0.00 |
FENCE FEE | $20.00 |
Z-FIELDS REIMBURSEMENT FEE | $0.00 |
RESIDENTIAL NEW PERMIT FEE | $1,829.70 |
RESIDENTIAL FEE | $161.97 |
RESIDENTIAL MECHANICAL FEE | $131.50 |
RESIDENTIAL NEW APPLICATION FEE | $300.00 |
RESIDENTIAL PLUMBING FEE | $213.00 |
SEWER IMPACT FEE | $2,344.00 |
THOROUGHFARE IMPACT FEE | $0.00 |
WATER IMPACT FEE | $2,174.00 |
PTO AND MECH ROUGH 08/09/2023 SMH | $30.00 |
PTO AND MECH ROUGH 08/11/2023 SMH | $30.00 |
UTILITIES INSPECTION 01/08/2024 TL | $100.00 |
Total Fees: | $8,465.97 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ T-POLE RES |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ SLAB RES |
______ SLAB RES |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ INSULATION RES |
______ INSULATION RES |
______ DRYWALL RES |
______ DRYWALL RES |
______ DRYWALL RES |
______ BRICKWALL TIES RES |
______ FLATWORK RES |
______ ELECT FINAL RES |
______ GAS RELEASE |
______ ELECT FINAL RES |
______ ELECT FINAL RES |
______ ELECT FINAL RES |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|