Seal BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 8/2/2023 PERMIT SUB-TYPE: CNEW PERMIT NO: B23-01874
JOB ADDRESS:
10575 NORTH COUNTY RD
FRISCO, TX 75033
DESC:   6016 SF, SHELL
OWNER:
FRISCO FLEX CENTER LP

DALLAS TX 75240-5780

CONTRACTOR:
S&H Design Development LLC
5437 Meadow Crest Dr.
Dallas TX 75229
ISSUED DATE:
8/2/2023
APPLIED DATE:
5/4/2023
EXPIRED DATE:
3/4/2025
SITE APN:
ADD332258
STATUS:
ISSUED
APPLICANT:
Jacob Hendershot
17120 Dallas Pkwy,
Dallas TX 75248
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
608722
FEE SUMMARY
INSPECTION SUMMARY
SLAB COMM 11/22/2023 CW$35.00
BUILDING FINAL 08/28/2024 CW$35.00
PERCENT CREDIT CARD FEE$1.00
PERCENT CREDIT CARD FEE$0.70
PERCENT CREDIT CARD FEE$1.00
PERCENT CREDIT CARD FEE$34.10
PERCENT CREDIT CARD FEE$0.70
COMM BUILDING PERMIT FEE$50.00
COMM BUILDING PERMIT FEE$50.00
1 INCH PD METER$605.00
WATER METER DEPOSIT COMMERCIAL$1,100.00
AUTO PROCESSING FEE$6.00
COMMERCIAL FEE$270.64
COMMERCIAL BUILDING PERMIT FEE$1,950.90
COMMERCIAL MECHANICAL FEE$43.50
COMMERCIAL NEW APPLICATION FEE$300.00
COMMERCIAL PLUMBING FEE$571.44
SEWER IMPACT FEE$0.00
THOROUGHFARE IMPACT FEE$0.00
WATER IMPACT FEE$0.00
Total Fees:$5,054.98
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  FIRELANE INSPECTION
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  SHEATHING COMM
______  PAVING
______  BRICKWALL TIE COMM
______  CMUWALL
______  PAVING
______  FLATWORK COMM
______  ELECT ROUGH COMM
______  GAS PRESSURE
______  PLUMB TOP OUT COMM
______  FRAME COMM
______  PLUMB TOP OUT COMM
______  FRAME COMM
______  FIRELANE INSPECTION
______  METER PAYMENT
______  SET 1 PD METER
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  PLUMBING FINAL
______  FIRE FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  BUILDING FINAL
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)

(THIS IS A BASIC PERMIT VIEW ONLY)