Seal BUILDING
Permit Payment Receipt


CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 5/23/2023 PERMIT SUB-TYPE: SNEW PERMIT NO: B23-01840
JOB ADDRESS:
15578 CRAPE MYRTLE RD
FRISCO, TX 75035
DESC:   2680 AC, 3438 SF, 2 STORY
OWNER:
HOMES LTD SHADDOCK
2400 DALLAS PKWY STE 460
PLANO TX 75093-4381

CONTRACTOR:
SHADDOCK HOMES LTD
2400 DALLAS PKWY STE 460
PLANO TX 75093
ISSUED DATE:
5/23/2023
APPLIED DATE:
5/2/2023
EXPIRED DATE:
10/26/2024
SITE APN:
ADD280734
STATUS:
COMPLETED
APPLICANT:
Erin Storm
2400 Dallas Parkway
Plano TX 75093
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
0
FEE SUMMARY
INSPECTION SUMMARY
SLAB RES 07/14/2023 DP2$30.00
PERCENT CREDIT CARD FEE$2.40
PERCENT CREDIT CARD FEE$2.40
2NDS AND FRAMING 10/17/2023 GLQ$30.00
BRICKWALL TIES RES 11/07/2023 GLQ$30.00
1 INCH PD METER$540.00
WATER METER DEPOSIT$150.00
GAS RELEASE 12/19/2023 MLM$30.00
AUTO PROCESSING FEE$6.00
FENCE FEE$20.00
Z-FIELDS REIMBURSEMENT FEE$0.00
RESIDENTIAL NEW PERMIT FEE$1,187.84
RESIDENTIAL FEE$101.28
RESIDENTIAL MECHANICAL FEE$108.50
RESIDENTIAL NEW APPLICATION FEE$300.00
RESIDENTIAL PLUMBING FEE$192.00
SEWER IMPACT FEE$0.00
THOROUGHFARE IMPACT FEE$1,337.00
WATER IMPACT FEE$2,120.00
PTO AND MECH ROUGH 09/15/2023 SDC$30.00
PTO AND MECH ROUGH 09/27/2023 SDC$30.00
PLUMB MECH FINAL 02/20/2024 SME2$30.00
PLUMB MECH FINAL 03/12/2024 SME2$30.00
Total Fees:$6,307.42
______  SET 1 PD METER
______  PLUMBING ROUGH-IN
______  T-POLE RES
______  SLAB RES
______  SLAB RES
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  PTO AND MECH ROUGH
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  2NDS AND FRAMING
______  INSULATION RES
______  BRICKWALL TIES RES
______  DRYWALL RES
______  BRICKWALL TIES RES
______  GAS RELEASE
______  ELECT FINAL RES
______  ELECT FINAL RES
______  FLATWORK RES
______  GAS RELEASE
______  GAS RELEASE
______  PLUMB MECH FINAL
______  UTILITIES INSPECTION
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  PLUMB MECH FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
______  CO AND BUILD FINAL
______  METER PAYMENT
Notes: