APPROVED DATE: 6/6/2023
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B23-01762
|
JOB ADDRESS: 15681 FRINGE TREE RD FRISCO, TX 75035 |
DESC:
2918 AC, 3475 SF , 2 STORY |
|
OWNER:
HOMES LTD SHADDOCK
2400 DALLAS PKWY STE 460 PLANO TX 75093-4381
|
CONTRACTOR:
SHADDOCK HOMES LTD
2400 DALLAS PKWY STE 460 PLANO TX 75093
|
ISSUED DATE: 6/6/2023
APPLIED DATE:4/27/2023
EXPIRED DATE:11/12/2024
SITE APN:ADD280713
STATUS:COMPLETED
|
|
APPLICANT:
Erin Storm
2400 Dallas Parkway Plano TX 75093
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
PLAN REVIEW FEE | $50.00 |
FLATWORK RES 03/20/2024 DW2 | $30.00 |
PERCENT CREDIT CARD FEE | $6.00 |
PERCENT CREDIT CARD FEE | $2.40 |
PERCENT CREDIT CARD FEE | $2.40 |
PERCENT CREDIT CARD FEE | $2.40 |
2NDS AND FRAMING 10/24/2023 GLQ | $30.00 |
DRYWALL RES 11/20/2023 JDR | $30.00 |
FLATWORK RES 03/04/2024 JDR | $30.00 |
FLATWORK RES 03/06/2024 JDR | $30.00 |
FLATWORK RES 03/11/2024 JDR | $30.00 |
SET 1 PD METER 06/23/2023 JRC | $100.00 |
SET 1 PD METER 07/06/2023 JRC | $100.00 |
SET 1 PD METER 07/12/2023 JRC | $100.00 |
PTO AND MECH ROUGH 09/18/2023 MLM | $30.00 |
PLUMB MECH FINAL 04/30/2024 MLM | $30.00 |
AUTO PROCESSING FEE | $6.00 |
FENCE FEE | $20.00 |
Z-FIELDS REIMBURSEMENT FEE | $0.00 |
RESIDENTIAL NEW PERMIT FEE | $1,221.50 |
RESIDENTIAL FEE | $104.25 |
RESIDENTIAL MECHANICAL FEE | $128.50 |
RESIDENTIAL NEW APPLICATION FEE | $300.00 |
RESIDENTIAL PLUMBING FEE | $192.00 |
SEWER IMPACT FEE | $0.00 |
THOROUGHFARE IMPACT FEE | $1,337.00 |
WATER IMPACT FEE | $2,120.00 |
FLATWORK RES 03/13/2024 RWK | $30.00 |
2NDS AND FRAMING 10/25/2023 RWT | $30.00 |
PTO AND MECH ROUGH 09/27/2023 SDC | $30.00 |
GAS RELEASE 02/26/2024 SME2 | $30.00 |
1 INCH PD METER | $540.00 |
WATER METER DEPOSIT | $150.00 |
Total Fees: | $6,842.45 |
|
|
| ______ SET 1 PD METER |
______ T-POLE RES |
______ PLUMBING ROUGH-IN |
______ SET 1 PD METER |
______ SET 1 PD METER |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ SLAB RES |
______ SLAB RES |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ DRYWALL RES |
______ DRYWALL RES |
______ BRICKWALL TIES RES |
______ BRICKWALL TIES RES |
______ ELECT FINAL RES |
______ GAS RELEASE |
______ FLATWORK RES |
______ FLATWORK RES |
______ 2NDS AND FRAMING |
______ FLATWORK RES |
______ FLATWORK RES |
______ FLATWORK RES |
______ FLATWORK RES |
______ FLATWORK RES |
______ GAS RELEASE |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
______ METER PAYMENT |
|
|
|