APPROVED DATE: 2/12/2024
|
PERMIT SUB-TYPE: CNEW
|
PERMIT NO: B23-01694
|
JOB ADDRESS: 10050 COIT RD FRISCO, TX 75035 |
DESC:
8420 SF, BEST BRAINS BLDG A4 |
|
OWNER:
KMPS DEVELOPMENT LLC
FAIRVIEW TX 75069-1526
|
CONTRACTOR:
KREA CONSTRUCTION
14114 Dallas Parkway STE 600 Dallas TX 75254
|
ISSUED DATE: 2/12/2024
APPLIED DATE:4/24/2023
EXPIRED DATE:5/14/2025
SITE APN:ADD331453
STATUS:ISSUED
|
|
APPLICANT:
Greg Guerin
PO Box 53 Forney TX 75126
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 750000
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
2 INCH T-10 METER | $1,210.00 |
WATER METER DEPOSIT COMMERCIAL | $1,100.00 |
SET 2 T-10 METER 06/19/2024 CDR | $100.00 |
PERCENT CREDIT CARD FEE | $0.70 |
PERCENT CREDIT CARD FEE | $46.20 |
PERCENT CREDIT CARD FEE | $2.00 |
PLUMBING ROUGH-IN 06/17/2024 JWR | $35.00 |
AUTO PROCESSING FEE | $6.00 |
COMMERCIAL FEE | $366.80 |
COMMERCIAL BUILDING PERMIT FEE | $2,352.75 |
COMMERCIAL MECHANICAL FEE | $451.00 |
COMMERCIAL NEW APPLICATION FEE | $300.00 |
COMMERCIAL PLUMBING FEE | $787.80 |
SEWER IMPACT FEE | $0.00 |
THOROUGHFARE IMPACT FEE | $0.00 |
WATER IMPACT FEE | $0.00 |
Total Fees: | $6,758.25 |
|
|
| ______ FOOTINGS COMM |
______ ELECT ROUGH COMM |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ METER PAYMENT |
______ SET 2 T-10 METER |
______ SET 2 T-10 METER |
______ PLUMBING ROUGH-IN |
______ SLAB COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ FIRELANE INSPECTION |
______ ELECT ROUGH COMM |
______ PIER COMM |
______ CMUWALL |
______ SHEATHING COMM |
______ ELECT ROUGH COMM |
______ LATH COMM |
______ BRICKWALL TIE COMM |
______ LATH COMM |
______ FRAME COMM |
______ BRICKWALL TIE COMM |
______ INSULATION COMM |
______ PLUMB TOP OUT COMM |
______ PLUMB TOP OUT COMM |
______ FLATWORK COMM |
______ ELECT RELEASE COMM |
______ ELECT RELEASE COMM |
______ ELECT RELEASE COMM |
______ ELECT RELEASE COMM |
______ PLUMB TOP OUT COMM |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|