BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 5/5/2023
|
PERMIT SUB-TYPE: CIFO
|
PERMIT NO: B23-00575
|
JOB ADDRESS: 12955 MAIN ST 1000 FRISCO, TX 75035 |
DESC:
13715 SF, SARIGAMA MARKET PLACE- FRISCO |
|
OWNER:
SHRIVENSARA SGM CNM LLC
FRISCO TX 75035-0945
|
CONTRACTOR:
MJR ENGINEERING (GC)
3030 LBJ FWY SUITE 1150 DALLAS TX 75234
|
ISSUED DATE: 5/5/2023
APPLIED DATE:2/15/2023
EXPIRED DATE:2/8/2025
SITE APN:ADD278638
STATUS:COMPLETED
|
|
APPLICANT:
Zahid Islam
3204 San Patricio Dr PLANO TX 75025
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 1000000
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
ELECT ROUGH COMM 02/26/2024 CW | $35.00 |
HEALTH PLAN REVIEW | $100.00 |
PERCENT CREDIT CARD FEE | $1.00 |
PERCENT CREDIT CARD FEE | $2.80 |
PERCENT CREDIT CARD FEE | $0.70 |
PERCENT CREDIT CARD FEE | $4.70 |
PERCENT CREDIT CARD FEE | $0.70 |
COMM BUILDING PERMIT FEE | $50.00 |
COMM BUILDING PERMIT FEE | $50.00 |
COMM BUILDING PERMIT FEE | $50.00 |
HEALTH FINAL 06/27/2024 JLE | $35.00 |
HEALTH FINAL 07/12/2024 JLE | $35.00 |
PLUMBING FINAL 04/09/2024 MLM | $35.00 |
AUTO PROCESSING FEE | $3.00 |
COMMERCIAL FEE | $578.60 |
COMMERCIAL MECHANICAL FEE | $715.75 |
COMMERCIAL PLUMBING FEE | $1,264.35 |
COMMERCIAL RENOVATION APPLICATION FEE | $150.00 |
COMMERCIAL RENOVATION FEE | $3,215.25 |
AUTO PROCESSING FEE | $115.48 |
GAS PRESSURE 02/02/2024 SME2 | $35.00 |
MECHANICAL ROUGH 03/01/2024 SME2 | $35.00 |
GAS RELEASE 03/21/2024 SME2 | $35.00 |
Total Fees: | $6,547.33 |
|
|
| ______ GREASE TRAP |
______ PLUMBING ROUGH-IN |
______ GREASE TRAP |
______ MECHANICAL ROUGH |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ SMOKE TEST |
______ PLUMB TOP OUT COMM |
______ PLUMB TOP OUT COMM |
______ PLUMB TOP OUT COMM |
______ FRAME COMM |
______ INSULATION COMM |
______ ELECT ROUGH COMM |
______ DRYWALL COMM |
______ DRYWALL COMM |
______ GAS PRESSURE |
______ GAS PRESSURE |
______ ELECT ROUGH COMM |
______ CEILING |
______ GAS PRESSURE |
______ MECHANICAL ROUGH |
______ MECHANICAL ROUGH |
______ MECHANICAL ROUGH |
______ MECHANICAL ROUGH |
______ CEILING |
______ ELECT RELEASE COMM |
______ GAS RELEASE |
______ PLUMBING FINAL |
______ GAS RELEASE |
______ ELECT RELEASE COMM |
______ CEILING |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ MECHANICAL FINAL |
______ COURTESY HEALTH INSP |
______ HEALTH FINAL |
______ HEALTH FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ HEALTH FINAL |
______ HEALTH FINAL |
______ FIRE FINAL |
______ INSPECTION ASSIST |
______ COMM CO |
______ FIRE FINAL |
______ MECHANICAL FINAL |
______ MECHANICAL FINAL |
______ MECHANICAL FINAL |
______ ELECT FINAL COMM |
______ ELECT FINAL COMM |
______ COMM CO |
______ COMM CO |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|