BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 7/26/2023
|
PERMIT SUB-TYPE: CNEW
|
PERMIT NO: B23-00458
|
JOB ADDRESS: 899 UNIVERSITY DR FRISCO, TX 75033 |
DESC:
130680 SF, HEB |
|
OWNER:
HEB GROCERY COMPANY LP
SAN ANTONIO TX 78283
|
CONTRACTOR:
EMJ CORPORATION (GC)
5525 N MACARTHUR BLVD IRVING TX 75038
|
ISSUED DATE: 7/26/2023
APPLIED DATE:2/6/2023
EXPIRED DATE:2/1/2025
SITE APN:ADD324645
STATUS:COMPLETED
|
|
APPLICANT:
Allison Hutton
2002 E 6th St Tulsa OK 74104
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 32224625
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
ELECT ROUGH COMM 05/23/2024 CW | $35.00 |
HEALTH FINAL 07/15/2024 DML | $35.00 |
HEALTH FINAL 07/24/2024 DML | $35.00 |
PERCENT CREDIT CARD FEE | $76.00 |
PERCENT CREDIT CARD FEE | $0.70 |
PERCENT CREDIT CARD FEE | $0.70 |
PERCENT CREDIT CARD FEE | $1.40 |
PERCENT CREDIT CARD FEE | $0.70 |
3 INCH COMP METER | $2,700.00 |
WATER METER DEPOSIT COMMERCIAL | $1,100.00 |
AUTO PROCESSING FEE | $6.00 |
COMMERCIAL FEE | $5,257.20 |
COMMERCIAL BUILDING PERMIT FEE | $62,080.50 |
COMMERCIAL MECHANICAL FEE | $6,564.00 |
COMMERCIAL NEW APPLICATION FEE | $300.00 |
COMMERCIAL PLUMBING FEE | $11,791.20 |
SEWER IMPACT FEE | $23,436.00 |
THOROUGHFARE IMPACT FEE | $1,127,336.00 |
WATER IMPACT FEE | $50,266.00 |
SMOKE TEST 06/27/2024 SMH | $35.00 |
PLUMBING FINAL 07/12/2024 SMH | $35.00 |
Total Fees: | $1,291,091.40 |
|
|
| ______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ ELECT ROUGH COMM |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ ELECT ROUGH COMM |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ ELECT ROUGH COMM |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ ELECT ROUGH COMM |
______ GREASE TRAP |
______ PLUMBING ROUGH-IN |
______ ELECT ROUGH COMM |
______ GREASE TRAP |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ FIRELANE INSPECTION |
______ FIRELANE INSPECTION |
______ PLUMBING ROUGH-IN |
______ ELECT ROUGH COMM |
______ PLUMBING ROUGH-IN |
______ CMUWALL |
______ ELECT ROUGH COMM |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ UNDERGROUND ELEC |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ CMUWALL |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ METER PAYMENT |
______ SET 3IN CMPND METER |
______ PLUMB TOP OUT COMM |
______ FRAME COMM |
______ CONSTRUCTION SAFETY |
______ FRAME AND ELEC WALL |
______ PLUMB TOP OUT COMM |
______ PLUMB TOP OUT COMM |
______ FRAME AND ELEC WALL |
______ PLUMB TOP OUT COMM |
______ ELECT RELEASE COMM |
______ FRAME AND ELEC WALL |
______ GAS PRESSURE |
______ PLUMB TOP OUT COMM |
______ GAS PRESSURE |
______ FRAME AND ELEC WALL |
______ FRAME AND ELEC WALL |
______ FLATWORK COMM |
______ PLUMB TOP OUT COMM |
______ FRAME AND ELEC WALL |
______ INSULATION COMM |
______ FRAME AND ELEC WALL |
______ INSULATION COMM |
______ MECHANICAL ROUGH |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ INSULATION COMM |
______ MEETING |
______ ELECT ROUGH COMM |
______ MECHANICAL ROUGH |
______ CEILING |
______ CONSTRUCTION SAFETY |
______ INSPECTION ASSIST |
______ FRAME COMM |
______ ELECT ROUGH COMM |
______ INSULATION COMM |
______ ELECT ROUGH COMM |
______ GAS PRESSURE |
______ GAS RELEASE |
______ CEILING |
______ CEILING |
______ ELECT RELEASE COMM |
______ MECHANICAL ROUGH |
______ COURTESY HEALTH INSP |
______ GAS PRESSURE |
______ SMOKE TEST |
______ SMOKE TEST |
______ CEILING |
______ CEILING |
______ PLUMBING FINAL |
______ MECHANICAL FINAL |
______ ELECT FINAL COMM |
______ HEALTH FINAL |
______ HEALTH FINAL |
______ ELECT FINAL COMM |
______ PLUMBING FINAL |
______ MECHANICAL FINAL |
______ FIRE FINAL |
______ INSPECTION ASSIST |
______ COMM CO |
______ HEALTH FINAL |
______ FIRE FINAL |
______ INSPECTION ASSIST |
______ LIFESAFETY |
______ HEALTH FINAL |
______ COMM CO |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|