BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 2/16/2023
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B23-00196
|
JOB ADDRESS: 3814 GRAPESEED DR FRISCO, TX 75033 |
DESC:
4021 AC, 5073 SF, 2 STORY *MODEL* |
|
OWNER:
FHQ HOLDINGS LP
1900 N AKARD ST DALLAS TX 75201
|
CONTRACTOR:
TOLL BROTHERS INC (GEN)
2555 SW Grapevine Pkwy, Suite 100 Grapevine TX 76051
|
ISSUED DATE: 2/16/2023
APPLIED DATE:2/16/2023
EXPIRED DATE:2/24/2024
SITE APN:ADD314473
STATUS:COMPLETED
|
|
APPLICANT:
Terah Montague
2555 SW Grapevine Pkwy #100 Grapevine TX 76051
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
1 INCH PD METER | $450.00 |
WATER METER DEPOSIT | $150.00 |
PLUMB MECH FINAL 06/29/2023 CI | $30.00 |
PLUMB MECH FINAL 07/11/2023 CI | $30.00 |
ELECT FINAL RES 05/23/2023 CMM2 | $30.00 |
PLAN REVIEW FEE | $50.00 |
PERCENT CREDIT CARD FEE | $12.00 |
PERCENT CREDIT CARD FEE | $2.00 |
PERCENT CREDIT CARD FEE | $2.40 |
PERCENT CREDIT CARD FEE | $1.20 |
PERCENT CREDIT CARD FEE | $1.80 |
PERCENT CREDIT CARD FEE | $12.00 |
SET 1 PD METER 02/17/2023 JAM3 | $100.00 |
2NDS AND FRAMING 04/11/2023 JDR | $30.00 |
INSULATION RES 04/18/2023 JDR | $30.00 |
AUTO PROCESSING FEE | $6.00 |
FENCE FEE | $20.00 |
Z-FIELDS REIMBURSEMENT FEE | $4,257.00 |
RESIDENTIAL NEW PERMIT FEE | $1,731.90 |
RESIDENTIAL FEE | $152.19 |
RESIDENTIAL MECHANICAL FEE | $135.00 |
RESIDENTIAL NEW APPLICATION FEE | $300.00 |
RESIDENTIAL PLUMBING FEE | $278.00 |
SEWER IMPACT FEE | $2,450.00 |
THOROUGHFARE IMPACT FEE | $0.00 |
WATER IMPACT FEE | $2,884.00 |
AUTO PROCESSING FEE | $239.16 |
PTO AND MECH ROUGH 04/04/2023 SDC | $30.00 |
PTO AND MECH ROUGH 04/05/2023 SDC | $30.00 |
GAS RELEASE 06/01/2023 SDC | $30.00 |
PTO AND MECH ROUGH 03/31/2023 SMH | $30.00 |
UTILITIES INSPECTION 08/02/2023 TL | $100.00 |
REPLACE DAMAGED/UNREADABLE REGISTER | $500.00 |
Total Fees: | $14,104.65 |
|
|
| ______ METER PAYMENT |
______ T-POLE RES |
______ SET 1 PD METER |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB RES |
______ SHEATHING RES |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ INSULATION RES |
______ DRYWALL RES |
______ LATH RES |
______ LATH RES |
______ ELECT FINAL RES |
______ ELECT FINAL RES |
______ ELECT FINAL RES |
______ GAS RELEASE |
______ GAS RELEASE |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ FLATWORK RES |
______ PLUMB MECH FINAL |
______ UTILITIES INSPECTION |
______ WATER REGISTER |
______ CO AND BUILD FINAL |
______ UTILITIES INSPECTION |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
|
|
|