BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 8/8/2022
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B22-03821
|
JOB ADDRESS: 11576 DAWN MIST DR FRISCO, TX 75035 |
DESC:
3131 AC, 3819 SF, 2 STORY |
|
OWNER:
FRISCO PROPERTY LLC 124
1605 LBJ FWY STE 700 DALLAS TX 75234-6099
|
CONTRACTOR:
MATTAMY TEXAS, LLC
1801 Wittinton Place, Suite 100 Farmers Branch TX 75234
|
ISSUED DATE: 8/8/2022
APPLIED DATE:8/8/2022
EXPIRED DATE:8/8/2023
SITE APN:ADD269921
STATUS:COMPLETED
|
|
APPLICANT:
Brandi Smith
1800 Valley View Lane Farmers Branch TX 75234
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
1 INCH PD METER | $450.00 |
WATER METER DEPOSIT | $150.00 |
PTO AND MECH ROUGH 02/09/2023 DOT | $30.00 |
FLATWORK RES 05/16/2023 DWF | $30.00 |
FLATWORK RES 05/24/2023 DWF | $30.00 |
PERCENT CREDIT CARD FEE | $12.00 |
PERCENT CREDIT CARD FEE | $4.00 |
PERCENT CREDIT CARD FEE | $2.40 |
PERCENT CREDIT CARD FEE | $0.60 |
PERCENT CREDIT CARD FEE | $0.00 |
PERCENT CREDIT CARD FEE | $2.40 |
PERCENT CREDIT CARD FEE | $0.60 |
PERCENT CREDIT CARD FEE | $4.00 |
FLATWORK RES 06/07/2023 JR2 | $30.00 |
SET 1 PD METER 09/20/2022 JRC | $100.00 |
SET 1 PD METER 09/21/2022 JRC | $100.00 |
FLATWORK RES 05/31/2023 JWE2 | $30.00 |
AUTO PROCESSING FEE | $6.00 |
FENCE FEE | $20.00 |
Z-FIELDS REIMBURSEMENT FEE | $0.00 |
RESIDENTIAL NEW PERMIT FEE | $1,335.27 |
RESIDENTIAL FEE | $114.57 |
RESIDENTIAL MECHANICAL FEE | $146.00 |
RESIDENTIAL NEW APPLICATION FEE | $300.00 |
RESIDENTIAL PLUMBING FEE | $242.00 |
SEWER IMPACT FEE | $2,344.00 |
THOROUGHFARE IMPACT FEE | $2,427.00 |
WATER IMPACT FEE | $2,168.00 |
SLAB RES 11/09/2022 PJF | $30.00 |
SLAB RES 11/01/2022 RWK | $30.00 |
SLAB RES 11/02/2022 RWK | $30.00 |
SLAB RES 11/04/2022 RWK | $30.00 |
GAS RELEASE 06/01/2023 SDC | $30.00 |
UTILITIES INSPECTION 07/03/2023 TL | $100.00 |
UTILITIES INSPECTION 07/07/2023 TL | $100.00 |
AUTO PROCESSING FEE | $175.94 |
Total Fees: | $10,604.78 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ SET 1 PD METER |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ SLAB RES |
______ SLAB RES |
______ SLAB RES |
______ SLAB RES |
______ SLAB RES |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ DRYWALL RES |
______ BRICKWALL TIES RES |
______ T-POLE RES |
______ FLATWORK RES |
______ FLATWORK RES |
______ ELECT FINAL RES |
______ FLATWORK RES |
______ GAS RELEASE |
______ GAS RELEASE |
______ FLATWORK RES |
______ FLATWORK RES |
______ UTILITIES INSPECTION |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|