Seal BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
APPROVED DATE: 10/25/2022 PERMIT SUB-TYPE: MNEW PERMIT NO: B22-03266
JOB ADDRESS:
10221 WHISTLE STOP LN
FRISCO, TX 75033
DESC:   719185 SF, JEFFERSON RAILHEAD APARTMENTS
OWNER:
JEFFERSON RAILHEAD (PHASE 1) LLC

IRVING TX 75039

CONTRACTOR:
JPI CONSTRUCTION
600 E LAS COLINAS BLVD. STE 1800
IRVING TX 75039
ISSUED DATE:
10/25/2022
APPLIED DATE:
6/27/2022
EXPIRED DATE:
5/14/2025
SITE APN:
ADD311160
STATUS:
ISSUED
APPLICANT:
Matthew Crow
600 East Las Colinas Blvd
Irving TX 75039
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
73400000
FEE SUMMARY
INSPECTION SUMMARY
SLAB COMM 05/24/2023 CW$35.00
PERCENT CREDIT CARD FEE$0.70
PERCENT CREDIT CARD FEE$3.80
PERCENT CREDIT CARD FEE$0.70
PERCENT CREDIT CARD FEE$3.00
PERCENT CREDIT CARD FEE$3.00
FIRE RATED WALL COMM 02/06/2024 JDR$35.00
FIRE RATED WALL COMM 02/26/2024 JDR$35.00
FIRE RATED WALL COMM 03/05/2024 JDR$35.00
FIRE RATED WALL COMM 02/19/2024 JDW2$35.00
BUILDING FINAL 09/03/2024 JDW2$35.00
CONSTRUCTION SAFETY 01/25/2024 JS3$50.00
FIRE FINAL 11/05/2024 JS3$150.00
FIRE FINAL 11/14/2024 JS3$150.00
AUTO PROCESSING FEE$6.00
COMMERCIAL FEE$28,797.40
COMMERCIAL BUILDING PERMIT FEE$139,903.14
COMMERCIAL MECHANICAL FEE$35,989.25
COMMERCIAL NEW APPLICATION FEE$300.00
COMMERCIAL PLUMBING FEE$64,756.65
SEWER IMPACT FEE$90,396.00
THOROUGHFARE IMPACT FEE$0.00
WATER IMPACT FEE$101,136.00
6 INCH COMP METER$7,915.00
WATER METER DEPOSIT COMMERCIAL$1,100.00
Total Fees:$470,870.64
______  FOOTINGS COMM
______  FOOTINGS COMM
______  FOOTINGS COMM
______  PLUMBING ROUGH-IN
______  FOOTINGS COMM
______  FOOTINGS COMM
______  ELECT ROUGH COMM
______  FOOTINGS COMM
______  FOOTINGS COMM
______  FOOTINGS COMM
______  PLUMBING ROUGH-IN
______  FOOTINGS COMM
______  FOOTINGS COMM
______  FOOTINGS COMM
______  PLUMBING ROUGH-IN
______  FOOTINGS COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  FOOTINGS COMM
______  SLAB COMM
______  ELECT ROUGH COMM
______  SLAB COMM
______  FOOTINGS COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  FIRELANE INSPECTION
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  FOOTINGS COMM
______  FIRELANE INSPECTION
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  PIER COMM
______  PIER COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  FOOTINGS COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  SHEATHING COMM
______  SLAB COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SHEATHING COMM
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  SLAB COMM
______  T-POLE COMM
______  ELECT RELEASE COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  SLAB COMM
______  SLAB COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  SLAB COMM
______  SHEATHING COMM
______  SLAB COMM
______  SHEATHING COMM
______  SHEATHING COMM
______  SHEATHING COMM
______  SHEATHING COMM
______  SHEATHING COMM
______  SLAB COMM
______  SHEATHING COMM
______  SHEATHING COMM
______  MEETING
______  SLAB COMM
______  SLAB COMM
______  SHEATHING COMM
______  SHEATHING COMM
______  SLAB COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  PLUMBING ROUGH-IN
______  MECHANICAL ROUGH
______  MECHANICAL ROUGH
______  CONSTRUCTION SAFETY
______  PLUMB TOP OUT COMM
______  FRAME COMM
______  PLUMB TOP OUT COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  FRAME COMM
______  FIRE RATED WALL COMM
______  FIRE RATED WALL COMM
______  PAVING
______  FIRE RATED WALL COMM
______  DRYWALL COMM
______  DRYWALL COMM
______  INSULATION COMM
______  FIRE RATED WALL COMM
______  DRYWALL COMM
______  LATH COMM
______  DRYWALL COMM
______  DRYWALL COMM
______  LATH COMM
______  FRAME COMM
______  FIRE RATED WALL COMM
______  FRAME COMM
______  PLUMB TOP OUT COMM
______  DRYWALL COMM
______  BRICKWALL TIE COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  PAVING
______  FIRE RATED WALL COMM
______  GAS PRESSURE
______  DRYWALL COMM
______  FRAME AND ELEC WALL
______  FLATWORK COMM
______  DRYWALL COMM
______  FLATWORK COMM
______  FIRE RATED WALL COMM
______  FRAME AND ELEC WALL
______  CEILING
______  FRAME COMM
______  MECHANICAL ROUGH
______  FIRE RATED WALL COMM
______  GAS PRESSURE
______  PLUMBING ROUGH-IN
______  FIRE RATED WALL COMM
______  FRAME AND ELEC WALL
______  DRYWALL COMM
______  FIRE RATED WALL COMM
______  CEILING
______  FRAME COMM
______  ELECT RELEASE COMM
______  FIRE RATED WALL COMM
______  CEILING
______  FRAME COMM
______  LATH COMM
______  FIRE RATED WALL COMM
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  ELECT RELEASE COMM
______  DRYWALL COMM
______  FRAME COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  ELECT RELEASE COMM
______  BRICKWALL TIE COMM
______  LATH COMM
______  DRYWALL COMM
______  SHEATHING COMM
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  PLUMB TOP OUT COMM
______  PLUMB TOP OUT COMM
______  ELECT ROUGH RES
______  MECHANICAL
______  PLUMB TOP OUT COMM
______  SHEATHING COMM
______  GREASE TRAP
______  BRICKWALL TIE COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  FRAME COMM
______  FRAME COMM
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  GAS PRESSURE
______  DRYWALL COMM
______  PLUMBING ROUGH-IN
______  DRYWALL COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  FRAME COMM
______  PLUMB TOP OUT COMM
______  FRAME COMM
______  DRYWALL COMM
______  DRYWALL COMM
______  FRAME COMM
______  FRAME RES
______  MECHANICAL ROUGH
______  FRAME COMM
______  BRICKWALL TIE COMM
______  ELECT ROUGH COMM
______  FRAME COMM
______  PLUMB TOP OUT COMM
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  PLUMB TOP OUT COMM
______  ELECTRICAL COMM
______  DRYWALL COMM
______  FRAME COMM
______  DRYWALL COMM
______  BRICKWALL TIE COMM
______  PLUMBING TOP OUT
______  BRICKWALL TIE COMM
______  FRAME COMM
______  FRAME COMM
______  FRAME COMM
______  DRYWALL COMM
______  BRICKWALL TIE COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  FRAME COMM
______  DRYWALL COMM
______  ELECT RELEASE COMM
______  ELECT RELEASE COMM
______  ELECT RELEASE COMM
______  ELECT ROUGH COMM
______  ELECT RELEASE COMM
______  ELECT RELEASE COMM
______  ELECT RELEASE COMM
______  FRAME COMM
______  DRYWALL COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  FRAME COMM
______  DRYWALL COMM
______  BRICKWALL TIE COMM
______  LATH COMM
______  LATH COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  FRAME COMM
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  FRAME COMM
______  BRICKWALL TIES RES
______  LATH COMM
______  BRICKWALL TIE COMM
______  PLUMB TOP OUT COMM
______  DRYWALL COMM
______  FRAME COMM
______  CONSTRUCTION SAFETY
______  INSPECTION ASSIST
______  INSPECTION ASSIST
______  DRYWALL COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  LATH COMM
______  DRYWALL COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  DRYWALL COMM
______  GAS RELEASE
______  ELECT RELEASE COMM
______  PLUMBING TOP OUT
______  DRYWALL COMM
______  DRYWALL COMM
______  DRYWALL COMM
______  FRAME COMM
______  FRAME COMM
______  DRYWALL COMM
______  ELECT RELEASE COMM
______  FRAME COMM
______  GAS PRESSURE
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  FRAME COMM
______  FRAME COMM
______  ELECT RELEASE COMM
______  FRAME COMM
______  GAS PRESSURE
______  LATH COMM
______  LATH COMM
______  LATH COMM
______  ELECT RELEASE COMM
______  BRICKWALL TIE COMM
______  CONSTRUCTION SAFETY
______  INSPECTION ASSIST
______  INSPECTION ASSIST
______  INSPECTION ASSIST
______  LATH COMM
______  FRAME COMM
______  FRAME COMM
______  BRICKWALL TIES RES
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  FRAME COMM
______  DRYWALL COMM
______  FRAME COMM
______  FRAME COMM
______  ELECT RELEASE COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  BRICKWALL TIES RES
______  ELECT ROUGH COMM
______  FRAME RES
______  FRAME RES
______  FRAME RES
______  ELECT FINAL RES
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  FRAME RES
______  LATH RES
______  LATH RES
______  METER PAYMENT
______  BUILDING FINAL
______  SET 6IN CMPND METER
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  BUILDING FINAL
______  FRAME COMM
______  FRAME COMM
______  FRAME COMM
______  ELECT ROUGH COMM
______  FRAME COMM
______  MECHANICAL ROUGH
______  BRICKWALL TIE COMM
______  PLUMB MECH FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  ELEVATOR
______  ELECT RELEASE COMM
______  ELECT RELEASE COMM
______  LATH COMM
______  BUILDING FINAL
______  ELECT FINAL COMM
______  PLUMB MECH FINAL
______  FIRE FINAL
______  ELECT FINAL COMM
______  BUILDING FINAL
______  COMM CO
______  BUILDING FINAL
______  ELECT FINAL COMM
______  PLUMB MECH FINAL
______  BUILDING FINAL
______  ELECT FINAL COMM
______  PLUMB MECH FINAL
______  BUILDING FINAL
______  PLUMB MECH FINAL
______  ELECT FINAL COMM
______  BUILDING FINAL
______  ELECT FINAL COMM
______  BUILDING FINAL
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  GAS
______  PLUMBING FINAL
______  BUILDING FINAL
______  FRAME COMM
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  FIRE FINAL
______  ELECT FINAL COMM
______  PLUMBING FINAL
______  MECHANICAL FINAL
______  FRAME COMM
______  FRAME COMM
______  FRAME COMM
______  FRAME COMM
______  LATH COMM
______  FRAME COMM
______  LATH COMM
______  FRAME COMM
______  BUILDING FINAL
______  ELECT FINAL COMM
______  PLUMB MECH FINAL
______  LATH COMM
______  BUILDING FINAL
______  FIRE FINAL
______  ELECT FINAL COMM
______  PLUMB MECH FINAL
______  FRAME COMM
______  FRAME COMM
______  FRAME COMM
______  ELECT RELEASE COMM
______  LIFESAFETY
______  COMM CO
______  COMM CO
______  FIRE FINAL
______  ELECT FINAL COMM
______  MECHANICAL FINAL
______  PLUMBING FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  BUILDING FINAL
______  ELECT FINAL COMM
______  PLUMB MECH FINAL
______  BUILDING FINAL
______  LIFESAFETY
______  FIRE FINAL
______  BUILDING FINAL
______  FIRE FINAL
______  FIRE FINAL
______  COMM CO
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)

(THIS IS A BASIC PERMIT VIEW ONLY)