APPROVED DATE: 12/21/2022 PERMIT SUB-TYPE: MNEW PERMIT NO: B22-02620
JOB ADDRESS:
12500 LIVE OAK WAY
FRISCO, TX 75035
DESC:   690973 SF, BRINKMANN RANCH PHASE 1
OWNER:
ABL APARTMENTS VENTURE LLC

DALLAS TX 75219-3916

CONTRACTOR:
MAPLE MULTI-FAMILY CONTRACTORS LLC
3889 Maple Ave.
Dallas TX 75219
ISSUED DATE:
12/21/2022
APPLIED DATE:
5/19/2022
EXPIRED DATE:
11/10/2024
SITE APN:
ADD350467
STATUS:
ISSUED
APPLICANT:
Claudio Campos
14881 Quorum Dr.
Dallas TX 75254
LEGAL DESC:
COUNTY:
ZONING:
VALUATION:
118000000
FEE SUMMARY
INSPECTION SUMMARY
PERCENT CREDIT CARD FEE$68.20
3 INCH COMP METER$3,225.00
WATER METER DEPOSIT COMMERCIAL$13,200.00
3 INCH COMP METER$3,225.00
3 INCH COMP METER$3,225.00
3 INCH COMP METER$3,225.00
3 INCH COMP METER$3,225.00
3 INCH COMP METER$3,225.00
3 INCH COMP METER$3,225.00
3 INCH COMP METER$3,225.00
3 INCH COMP METER$3,225.00
3 INCH COMP METER$3,225.00
3 INCH COMP METER$3,225.00
3 INCH COMP METER$3,225.00
1 INCH PD METER$1,210.00
WATER METER DEPOSIT COMMERCIAL$2,200.00
PLUMBING ROUGH-IN 06/08/2023 SDC$30.00
WATER IMPACT FEE$270,098.00
THOROUGHFARE IMPACT FEE$0.00
SEWER IMPACT FEE$287,928.00
COMMERCIAL PLUMBING FEE$62,217.57
COMMERCIAL NEW APPLICATION FEE$300.00
COMMERCIAL MECHANICAL FEE$34,578.65
COMMERCIAL BUILDING PERMIT FEE$224,197.14
COMMERCIAL FEE$27,668.92
AUTO PROCESSING FEE$6.00
SLAB COMM 08/01/2023 DC2$35.00
PERCENT CREDIT CARD FEE$1.30
Total Fees:$962,438.78
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  ELECT ROUGH COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  ELECT ROUGH COMM
______  SLAB COMM
______  ELECT ROUGH COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  ELECT ROUGH COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  SLAB COMM
______  ELECT ROUGH COMM
______  SLAB COMM
______  ELECT ROUGH COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  ELECT ROUGH COMM
______  SLAB COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  ELECT ROUGH COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  ELECT ROUGH COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  PLUMBING ROUGH-IN
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  SLAB COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  ELECT FINAL COMM
______  PAVING
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  PAVING
______  FIRELANE INSPECTION
______  PAVING
______  ELECT ROUGH COMM
______  PAVING
______  ELECT ROUGH COMM
______  PAVING
______  PAVING
______  PAVING
______  FIRELANE INSPECTION
______  PAVING
______  PAVING
______  FRAME COMM
______  FIRELANE INSPECTION
______  PAVING
______  CONSTRUCTION SAFETY
______  PAVING
______  PAVING
______  PAVING
______  SHEATHING COMM
______  FIRELANE INSPECTION
______  SHEATHING COMM
______  SHEATHING COMM
______  SHEATHING COMM
______  SHEATHING COMM
______  SHEATHING COMM
______  METER PAYMENT
______  BRICKWALL TIE COMM
______  SET 3IN CMPND METER
______  SET 3IN CMPND METER
______  SET 3IN CMPND METER
______  SET 3IN CMPND METER
______  SET 3IN CMPND METER
______  SET 3IN CMPND METER
______  SET 3IN CMPND METER
______  SET 3IN CMPND METER
______  SET 3IN CMPND METER
______  SET 3IN CMPND METER
______  SET 3IN CMPND METER
______  SET 3IN CMPND METER
______  METER PAYMENT
______  METER PAYMENT
______  SHEATHING COMM
______  BRICKWALL TIE COMM
______  PLUMB TOP OUT COMM
______  ELECT ROUGH COMM
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  ELECT ROUGH COMM
______  MECHANICAL ROUGH
______  SHEATHING COMM
______  MECHANICAL ROUGH
______  CEILING
______  LATH COMM
______  CEILING
______  ELECT ROUGH COMM
______  FIRE FINAL
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)