BUILDING
PERMIT
Inspections Line: 972.292.5386 cut-off at 4 PM the business day before
OR
Request Inspections online at https:\\etrakit.friscotexas.gov\etrakit until 7:00 AM same day
Contact assigned inspector for cancellation.
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 12/21/2022
|
PERMIT SUB-TYPE: MNEW
|
PERMIT NO: B22-02620
|
JOB ADDRESS: 12500 LIVE OAK WAY FRISCO, TX 75035 |
DESC:
690973 SF, BRINKMANN RANCH PHASE 1 |
|
OWNER:
ABL APARTMENTS VENTURE LLC
DALLAS TX 75219-3916
|
CONTRACTOR:
MAPLE MULTI-FAMILY CONTRACTORS LLC
3889 Maple Ave. Dallas TX 75219
|
ISSUED DATE: 12/21/2022
APPLIED DATE:5/19/2022
EXPIRED DATE:11/10/2024
SITE APN:ADD350467
STATUS:ISSUED
|
|
APPLICANT:
Claudio Campos
14881 Quorum Dr. Dallas TX 75254
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 118000000
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
PERCENT CREDIT CARD FEE | $68.20 |
3 INCH COMP METER | $3,225.00 |
WATER METER DEPOSIT COMMERCIAL | $13,200.00 |
3 INCH COMP METER | $3,225.00 |
3 INCH COMP METER | $3,225.00 |
3 INCH COMP METER | $3,225.00 |
3 INCH COMP METER | $3,225.00 |
3 INCH COMP METER | $3,225.00 |
3 INCH COMP METER | $3,225.00 |
3 INCH COMP METER | $3,225.00 |
3 INCH COMP METER | $3,225.00 |
3 INCH COMP METER | $3,225.00 |
3 INCH COMP METER | $3,225.00 |
3 INCH COMP METER | $3,225.00 |
1 INCH PD METER | $1,210.00 |
WATER METER DEPOSIT COMMERCIAL | $2,200.00 |
PLUMBING ROUGH-IN 06/08/2023 SDC | $30.00 |
WATER IMPACT FEE | $270,098.00 |
THOROUGHFARE IMPACT FEE | $0.00 |
SEWER IMPACT FEE | $287,928.00 |
COMMERCIAL PLUMBING FEE | $62,217.57 |
COMMERCIAL NEW APPLICATION FEE | $300.00 |
COMMERCIAL MECHANICAL FEE | $34,578.65 |
COMMERCIAL BUILDING PERMIT FEE | $224,197.14 |
COMMERCIAL FEE | $27,668.92 |
AUTO PROCESSING FEE | $6.00 |
SLAB COMM 08/01/2023 DC2 | $35.00 |
PERCENT CREDIT CARD FEE | $1.30 |
Total Fees: | $962,438.78 |
|
|
| ______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ PLUMBING ROUGH-IN |
______ SLAB COMM |
______ ELECT ROUGH COMM |
______ SLAB COMM |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ ELECT ROUGH COMM |
______ SLAB COMM |
______ ELECT ROUGH COMM |
______ SLAB COMM |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB COMM |
______ PLUMBING ROUGH-IN |
______ SLAB COMM |
______ SLAB COMM |
______ PLUMBING ROUGH-IN |
______ ELECT ROUGH COMM |
______ SLAB COMM |
______ PLUMBING ROUGH-IN |
______ SLAB COMM |
______ SLAB COMM |
______ ELECT ROUGH COMM |
______ SLAB COMM |
______ ELECT ROUGH COMM |
______ SLAB COMM |
______ PLUMBING ROUGH-IN |
______ ELECT ROUGH COMM |
______ SLAB COMM |
______ SLAB COMM |
______ PLUMBING ROUGH-IN |
______ SLAB COMM |
______ ELECT ROUGH COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ ELECT ROUGH COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ PLUMBING ROUGH-IN |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ SLAB COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT FINAL COMM |
______ PAVING |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ PAVING |
______ FIRELANE INSPECTION |
______ PAVING |
______ ELECT ROUGH COMM |
______ PAVING |
______ ELECT ROUGH COMM |
______ PAVING |
______ PAVING |
______ PAVING |
______ FIRELANE INSPECTION |
______ PAVING |
______ PAVING |
______ FRAME COMM |
______ FIRELANE INSPECTION |
______ PAVING |
______ CONSTRUCTION SAFETY |
______ PAVING |
______ PAVING |
______ PAVING |
______ SHEATHING COMM |
______ FIRELANE INSPECTION |
______ SHEATHING COMM |
______ SHEATHING COMM |
______ SHEATHING COMM |
______ SHEATHING COMM |
______ SHEATHING COMM |
______ METER PAYMENT |
______ BRICKWALL TIE COMM |
______ SET 3IN CMPND METER |
______ SET 3IN CMPND METER |
______ SET 3IN CMPND METER |
______ SET 3IN CMPND METER |
______ SET 3IN CMPND METER |
______ SET 3IN CMPND METER |
______ SET 3IN CMPND METER |
______ SET 3IN CMPND METER |
______ SET 3IN CMPND METER |
______ SET 3IN CMPND METER |
______ SET 3IN CMPND METER |
______ SET 3IN CMPND METER |
______ METER PAYMENT |
______ METER PAYMENT |
______ SHEATHING COMM |
______ BRICKWALL TIE COMM |
______ PLUMB TOP OUT COMM |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ MECHANICAL ROUGH |
______ ELECT ROUGH COMM |
______ MECHANICAL ROUGH |
______ SHEATHING COMM |
______ MECHANICAL ROUGH |
______ CEILING |
______ LATH COMM |
______ CEILING |
______ ELECT ROUGH COMM |
______ FIRE FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|