BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
|
APPROVED DATE: 5/19/2022
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B22-01182
|
| JOB ADDRESS: 3493 MIDWICK DR FRISCO, TX 75034 |
DESC:
7278 AC, 11167 SF, 2 STORY |
|
OWNER:
BUSTER CHANDLER BUILDER LLC
1110 JC LANE PILOT POINT TX 76258
|
CONTRACTOR:
4F Custom Homes and Framing, Inc.
155 Buck Creek Access Pilot Point TX 76258
|
|
ISSUED DATE: 5/19/2022
APPLIED DATE:5/17/2022
EXPIRED DATE:10/2/2024
SITE APN:ADD184235
STATUS:COMPLETED
|
|
APPLICANT:
Michael Fritz
155 Buck Creek Access Pilot Point TX 76258
| |
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
| SHEATHING RES 12/12/2022 CMM2 | $30.00 |
| SHEATHING RES 12/20/2022 CMM2 | $30.00 |
| LATH RES 03/31/2023 DC2 | $30.00 |
| 2NDS AND FRAMING 04/04/2023 DW2 | $30.00 |
| LATH RES 04/10/2023 DW2 | $30.00 |
| 2NDS AND FRAMING 04/11/2023 DW2 | $30.00 |
| DRYWALL RES 06/14/2023 DW2 | $30.00 |
| PERCENT CREDIT CARD FEE | $2.00 |
| PERCENT CREDIT CARD FEE | $0.60 |
| PERCENT CREDIT CARD FEE | $0.60 |
| PERCENT CREDIT CARD FEE | $2.60 |
| PERCENT CREDIT CARD FEE | $0.60 |
| PERCENT CREDIT CARD FEE | $2.00 |
| T-POLE RES 07/12/2022 GLQ | $30.00 |
| SET 2 T-10 METER 06/08/2022 JRC | $100.00 |
| AUTO PROCESSING FEE | $6.00 |
| FENCE FEE | $20.00 |
| RESIDENTIAL NEW PERMIT FEE | $3,373.42 |
| RESIDENTIAL FEE | $335.01 |
| RESIDENTIAL MECHANICAL FEE | $205.00 |
| RESIDENTIAL NEW APPLICATION FEE | $300.00 |
| RESIDENTIAL PLUMBING FEE | $312.00 |
| SEWER IMPACT FEE | $1,619.00 |
| THOROUGHFARE IMPACT FEE | $0.00 |
| WATER IMPACT FEE | $2,165.00 |
| AUTO PROCESSING FEE | $162.59 |
| PLAN REVIEW FEE | $100.00 |
| PTO AND MECH ROUGH 03/24/2023 SMH | $30.00 |
| UTILITIES INSPECTION 03/15/2024 TL | $100.00 |
| 2 INCH T-10 METER | $450.00 |
| WATER METER DEPOSIT | $150.00 |
| REPLACEMENT CARD FEE | $10.00 |
| SLAB RES 08/19/2022 GLQ | $30.00 |
| PERCENT CREDIT CARD FEE | $1.80 |
| CREDIT CARD FEE | $19.50 |
| Total Fees: | $9,737.72 |
|
|
|
| | ______ METER PAYMENT |
| ______ SET 2 T-10 METER |
| ______ SET 1 PD METER |
| ______ T-POLE RES |
| ______ T-POLE RES |
| ______ PLUMBING ROUGH-IN |
| ______ PLUMBING ROUGH-IN |
| ______ PLUMBING ROUGH-IN |
| ______ PLUMBING ROUGH-IN |
| ______ SLAB RES |
| ______ SLAB RES |
| ______ RETAIN WALL RES |
| ______ SHEATHING RES |
| ______ SHEATHING RES |
| ______ SHEATHING RES |
| ______ RETAIN WALL RES |
| ______ PTO AND MECH ROUGH |
| ______ ELECT ROUGH RES |
| ______ PTO AND MECH ROUGH |
| ______ PTO AND MECH ROUGH |
| ______ 2NDS AND FRAMING |
| ______ LATH RES |
| ______ 2NDS AND FRAMING |
| ______ ELECT ROUGH RES |
| ______ LATH RES |
| ______ 2NDS AND FRAMING |
| ______ LATH RES |
| ______ 2NDS AND FRAMING |
| ______ 2NDS AND FRAMING |
| ______ INSULATION RES |
| ______ LATH RES |
| ______ DRYWALL RES |
| ______ DRYWALL RES |
| ______ UTILITIES INSPECTION |
| ______ ELECT FINAL RES |
| ______ GAS RELEASE |
| ______ GAS RELEASE |
| ______ FLATWORK RES |
| ______ PLUMB MECH FINAL |
| ______ PLUMB MECH FINAL |
| ______ PLUMB MECH FINAL |
| ______ PLUMB MECH FINAL |
| ______ ELECT FINAL RES |
| ______ UTILITIES INSPECTION |
| ______ PLUMB MECH FINAL |
| ______ PLUMB MECH FINAL |
| ______ UTILITIES INSPECTION |
| ______ CO AND BUILD FINAL |
| ______ CO AND BUILD FINAL |
| ______ CO AND BUILD FINAL |
| ______ CO AND BUILD FINAL |
| ______ CO AND BUILD FINAL |
|
|
|
|