BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 4/8/2022
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B22-01001
|
JOB ADDRESS: 12363 HARVEST MEADOW DR FRISCO, TX 75033 |
DESC:
9096 AC, 12382 SF, 2 STORY |
|
OWNER:
NEWMAN VILLAGE CONSTRUCTION LLC
9801 CAMFIELD WAY FRISCO TX 75033
|
CONTRACTOR:
COATS HOMES LLC
3100 MONTICELLO AVE STE 335 DALLAS TX 75205
|
ISSUED DATE: 4/8/2022
APPLIED DATE:4/8/2022
EXPIRED DATE:1/26/2025
SITE APN:ADD191840
STATUS:COMPLETED
|
|
APPLICANT:
Paul Harrison
3100 Monticello Ave. STE 335 Dallas TX 75205
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
ELECT FINAL RES 03/04/2024 RWT | $30.00 |
2NDS AND FRAMING 06/02/2023 JDR | $30.00 |
2NDS AND FRAMING 05/24/2023 JDR | $30.00 |
PLAN REVIEW FEE | $50.00 |
2NDS AND FRAMING 06/13/2023 CMM2 | $30.00 |
PLUMB MECH FINAL 06/24/2024 SMH | $30.00 |
WATER IMPACT FEE | $3,085.00 |
THOROUGHFARE IMPACT FEE | $5,322.00 |
SEWER IMPACT FEE | $2,294.00 |
RESIDENTIAL PLUMBING FEE | $373.00 |
RESIDENTIAL NEW APPLICATION FEE | $300.00 |
RESIDENTIAL MECHANICAL FEE | $225.00 |
RESIDENTIAL FEE | $371.46 |
RESIDENTIAL NEW PERMIT FEE | $3,689.32 |
FENCE FEE | $20.00 |
AUTO PROCESSING FEE | $6.00 |
WATER METER DEPOSIT | $150.00 |
1 INCH PD METER | $450.00 |
PERCENT CREDIT CARD FEE | $1.20 |
PERCENT CREDIT CARD FEE | $1.80 |
PERCENT CREDIT CARD FEE | $2.00 |
CREDIT CARD FEE | $12.00 |
AUTO PROCESSING FEE | $308.60 |
SET 1 PD METER 04/21/2022 JRC | $100.00 |
Total Fees: | $16,911.38 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ SET 1 PD METER |
______ T-POLE RES |
______ PIER RES |
______ PIER RES |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ SLAB RES |
______ SHEATHING RES |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ 2NDS AND FRAMING |
______ ELECT ROUGH RES |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ BRICKWALL TIES RES |
______ INSULATION RES |
______ DRYWALL RES |
______ BRICKWALL TIES RES |
______ T-POLE RES |
______ T-POLE RES |
______ GAS RELEASE |
______ ELECT FINAL RES |
______ GAS RELEASE |
______ ELECT FINAL RES |
______ FLATWORK RES |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ CO AND BUILD FINAL |
______ UTILITIES INSPECTION |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
|
|
|