APPROVED DATE: 1/27/2022
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B22-00263
|
JOB ADDRESS: 14632 FARMING RD FRISCO, TX 75035 |
DESC:
4044 AC, 4797 SF, 2 STORY |
|
OWNER:
TEXAS HOMES INC FIRST
500 CRESCENT CT STE 350 DALLAS TX 75201-7854
|
CONTRACTOR:
FIRST TEXAS CUSTOM HOMES
500 CRESCENT CT STE 350 DALLAS TX 75201
|
ISSUED DATE: 1/27/2022
APPLIED DATE:1/25/2022
EXPIRED DATE:8/23/2023
SITE APN:ADD279769
STATUS:COMPLETED
|
|
APPLICANT:
Ana Gutierrez
500 Crescent Court, Suite 350 Dallas TX 75201
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
2NDS AND FRAMING 09/01/2022 DW2 | $30.00 |
2NDS AND FRAMING 09/09/2022 DW2 | $30.00 |
CREDIT CARD FEE | $1.20 |
PERCENT CREDIT CARD FEE | $0.60 |
PERCENT CREDIT CARD FEE | $1.20 |
PERCENT CREDIT CARD FEE | $0.60 |
PERCENT CREDIT CARD FEE | $0.60 |
PERCENT CREDIT CARD FEE | $0.60 |
PERCENT CREDIT CARD FEE | $0.60 |
REPLACEMENT CARD FEE | $10.00 |
1 INCH PD METER | $450.00 |
AUTO PROCESSING FEE | $0.00 |
FENCE FEE | $20.00 |
RESIDENTIAL NEW PERMIT FEE | $1,647.07 |
RESIDENTIAL FEE | $143.91 |
RESIDENTIAL MECHANICAL FEE | $146.00 |
RESIDENTIAL NEW APPLICATION FEE | $300.00 |
RESIDENTIAL PLUMBING FEE | $256.00 |
SEWER IMPACT FEE | $2,344.00 |
THOROUGHFARE IMPACT FEE | $826.00 |
WATER IMPACT FEE | $2,137.00 |
INSULATION RES 10/05/2022 RWK | $30.00 |
UTILITIES INSPECTION 01/27/2023 TL | $100.00 |
UTILITIES INSPECTION 01/24/2023 TL | $100.00 |
GAS RELEASE 01/09/2023 MLM | $30.00 |
GAS RELEASE 01/05/2023 MLM | $30.00 |
SLAB RES 03/14/2022 JDR | $30.00 |
SLAB RES 03/09/2022 JDR | $30.00 |
PTO AND MECH ROUGH 08/10/2022 GU | $30.00 |
PERCENT CREDIT CARD FEE | $2.00 |
PERCENT CREDIT CARD FEE | $2.60 |
GAS RELEASE 12/20/2022 SME2 | $30.00 |
WATER METER DEPOSIT | $125.00 |
ELECT FINAL RES 01/20/2023 RWT | $30.00 |
PLAN REVIEW FEE | $50.00 |
Total Fees: | $8,964.98 |
|
|
| ______ METER PAYMENT |
______ T-POLE RES |
______ SET 1 PD METER |
______ PLUMBING ROUGH-IN |
______ SLAB RES |
______ SLAB RES |
______ SLAB RES |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ INSULATION RES |
______ INSULATION RES |
______ BRICKWALL TIES RES |
______ DRYWALL RES |
______ FLATWORK RES |
______ GAS RELEASE |
______ GAS RELEASE |
______ GAS RELEASE |
______ GAS RELEASE |
______ ELECT FINAL RES |
______ UTILITIES INSPECTION |
______ ELECT FINAL RES |
______ UTILITIES INSPECTION |
______ UTILITIES INSPECTION |
______ FLATWORK RES |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ PLUMB MECH FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
|
|
|