APPROVED DATE: 11/17/2021
|
PERMIT SUB-TYPE: SNEW
|
PERMIT NO: B21-05079
|
JOB ADDRESS: 6619 PEMBERTON DR FRISCO, TX 75034 |
DESC:
2860 AC, 3986 SF, 2 STORY |
|
OWNER:
HT STONEBROOK LAND I LP
2200 ROSS AVE STE 4200W DALLAS TX 75201
|
CONTRACTOR:
DFH Coventry Homes
7676 Woodway Houston TX 77063
|
ISSUED DATE: 11/17/2021
APPLIED DATE:11/17/2021
EXPIRED DATE:3/20/2023
SITE APN:ADD221529
STATUS:COMPLETED
|
|
APPLICANT:
MHI Homes
16980 N Dallas Pkwy Dallas TX 75248
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 0
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
SLAB RES 01/11/2022 DC2 | $30.00 |
CO AND BUILD FINAL 09/19/2022 DWF | $30.00 |
CREDIT CARD FEE | $11.50 |
1 INCH PD METER | $450.00 |
WATER METER DEPOSIT | $125.00 |
PLUMB MECH FINAL 09/13/2022 MLM | $30.00 |
AUTO PROCESSING FEE | $6.00 |
FENCE FEE | $20.00 |
RESIDENTIAL NEW PERMIT FEE | $1,390.38 |
RESIDENTIAL FEE | $119.58 |
RESIDENTIAL MECHANICAL FEE | $146.00 |
RESIDENTIAL NEW APPLICATION FEE | $300.00 |
RESIDENTIAL PLUMBING FEE | $240.00 |
SEWER IMPACT FEE | $2,344.00 |
THOROUGHFARE IMPACT FEE | $119.00 |
WATER IMPACT FEE | $2,151.00 |
AUTO PROCESSING FEE | $131.60 |
PLAN REVIEW FEE | $50.00 |
GAS RELEASE 07/29/2022 SMH | $30.00 |
UTILITIES INSPECTION 09/07/2022 TL | $100.00 |
Total Fees: | $7,824.06 |
|
|
| ______ METER PAYMENT |
______ SET 1 PD METER |
______ T-POLE RES |
______ PLUMBING ROUGH-IN |
______ SLAB RES |
______ SLAB RES |
______ T-POLE RES |
______ PTO AND MECH ROUGH |
______ PTO AND MECH ROUGH |
______ 2NDS AND FRAMING |
______ 2NDS AND FRAMING |
______ INSULATION RES |
______ DRYWALL RES |
______ BRICKWALL TIES RES |
______ BRICKWALL TIES RES |
______ LATH RES |
______ FLATWORK RES |
______ BRICKWALL TIES RES |
______ GAS RELEASE |
______ ELECT FINAL RES |
______ GAS RELEASE |
______ GAS RELEASE |
______ PLUMB MECH FINAL |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ TREE |
______ UTILITIES INSPECTION |
______ PLUMB MECH FINAL |
______ CO AND BUILD FINAL |
______ CO AND BUILD FINAL |
|
The project described shall be built in accordance with plans and specifications submitted at time of applications. All provisions of law and ordinances governing this type of work will be complied with whether specified or not. Granting of a permit does not presume to give authority to violate or cancel the provisions of any other local or state law regulating construction or the performance of construction. (The City will not assume responsibility for workability of sanitary sewer on all lots. NOTICE: A Certificate of Occupancy Must be Issued Before Any Building is Occupied.)
|
(THIS IS A BASIC PERMIT VIEW ONLY)
|
|