BUILDING
Permit Payment Receipt
|
CITY OF FRISCO
6101 Frisco Square Blvd, TX 75034
Phone: 972.292.5301
|
APPROVED DATE: 7/19/2022
|
PERMIT SUB-TYPE: CNEW
|
PERMIT NO: B21-04262
|
JOB ADDRESS: 10400 FRISCO ST BLDG 3 FRISCO, TX 75033 |
DESC:
16703 SF, ALLTRADES BUILDING 3 |
|
OWNER:
AIP FRISCO LLC
LEWISVILLE TX 75057-2330
|
CONTRACTOR:
ATI GC dba Eagle Court
1504 Eagle Court Lewisville TX 75057
|
ISSUED DATE: 7/19/2022
APPLIED DATE:8/31/2021
EXPIRED DATE:8/6/2025
SITE APN:ADD291932
STATUS:COMPLETED
|
|
APPLICANT:
John Lam
520 South Main Street, Suite 2531 Akron OH 44311
|
LEGAL DESC:
COUNTY:
ZONING:
VALUATION: 1270000
|
|
FEE SUMMARY
|
INSPECTION SUMMARY
|
FRAME AND ELEC WALL 03/24/2023 CW | $35.00 |
DRYWALL COMM 08/10/2023 CW | $35.00 |
INSULATION COMM 06/29/2023 DC2 | $35.00 |
PERCENT CREDIT CARD FEE | $42.00 |
PERCENT CREDIT CARD FEE | $3.50 |
PERCENT CREDIT CARD FEE | $1.40 |
AUTO PROCESSING FEE | $6.00 |
COMMERCIAL FEE | $698.12 |
COMMERCIAL BUILDING PERMIT FEE | $3,577.44 |
COMMERCIAL MECHANICAL FEE | $865.15 |
COMMERCIAL NEW APPLICATION FEE | $300.00 |
COMMERCIAL PLUMBING FEE | $1,533.27 |
SEWER IMPACT FEE | $0.00 |
THOROUGHFARE IMPACT FEE | $0.00 |
WATER IMPACT FEE | $0.00 |
AUTO PROCESSING FEE | $50.05 |
FRAME COMM 06/09/2023 REED | $35.00 |
GAS RELEASE 09/06/2024 SME2 | $35.00 |
PLUMBING FINAL 09/20/2024 SME2 | $35.00 |
PLUMBING FINAL 10/18/2024 SMH | $35.00 |
2 INCH T-10 METER | $1,000.00 |
WATER METER DEPOSIT COMMERCIAL | $1,100.00 |
Total Fees: | $9,421.93 |
|
|
| ______ ELECT ROUGH COMM |
______ COURTESY FIRE |
______ ELECT ROUGH COMM |
______ UNDRGR FIRE MAIN HYD |
______ UNDRGR FIRE MAIN VIS |
______ UNDRGR FIRE MAIN FLU |
______ PLUMBING ROUGH-IN |
______ PLUMBING ROUGH-IN |
______ FIRELANE INSPECTION |
______ SHEATHING COMM |
______ ELECT ROUGH COMM |
______ BRICKWALL TIE COMM |
______ MECHANICAL ROUGH |
______ MECHANICAL ROUGH |
______ PLUMB TOP OUT COMM |
______ PLUMB TOP OUT COMM |
______ FIRELANE INSPECTION |
______ FRAME AND ELEC WALL |
______ FRAME AND ELEC WALL |
______ BRICKWALL TIE COMM |
______ FRAME AND ELEC WALL |
______ BRICKWALL TIE COMM |
______ BRICKWALL TIE COMM |
______ GAS PRESSURE |
______ FRAME AND ELEC WALL |
______ FRAME COMM |
______ FRAME COMM |
______ FRAME COMM |
______ FIRE RATED WALL COMM |
______ INSULATION COMM |
______ INSULATION COMM |
______ GAS PRESSURE |
______ GAS RELEASE |
______ METER PAYMENT |
______ DRYWALL COMM |
______ GAS RELEASE |
______ FRAME COMM |
______ INSULATION COMM |
______ DRYWALL COMM |
______ SET 2 T-10 METER |
______ ELECT ROUGH COMM |
______ ELECT ROUGH COMM |
______ ELECT RELEASE COMM |
______ BRICKWALL TIE COMM |
______ ELECT FINAL COMM |
______ ELECT FINAL COMM |
______ ELECT FINAL COMM |
______ ELECT FINAL COMM |
______ ELECT FINAL COMM |
______ ELECT FINAL COMM |
______ GAS RELEASE |
______ PLUMBING FINAL |
______ GAS RELEASE |
______ GAS RELEASE |
______ MECHANICAL FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ PLUMBING FINAL |
______ FIRE FINAL |
______ BUILDING FINAL |
______ FIRE FINAL |
______ BUILDING FINAL |
______ BUILDING FINAL |
______ BUILDING FINAL |
|
|
|